Take Me To The River, Part 2, Schedule Elements–A Digital Inventory of Integrated Program Management Elements

Recent attendance at various forums to speak has interrupted the flow of this series on IPM elements. Among these venues I was engaged in discussions regarding this topic, as well as the effects of acquisition reform on the IT, program, and project management communities in the DoD and A&D marketplace.

For this post I will restrict the topic to what are often called schedule elements, though that is a nebulous term. Also, one should not draw a conclusion that because I am dealing with this topic following cost elements, that it is somehow inferior in importance to those elements. On the contrary, planning and scheduling are integral to applying resources and costs, in tracking cost performance, and in our systemic analysis its activities, artifacts, and elements are antecedent to cost element considerations.

The Relative Position of Schedule

But the takeaway here is this: under no circumstances should any program or project manager believe that cost and schedule systems represent a dichotomy, nor a hierarchy, of disciplines. They are interdependent and the behavior noted in one will be manifested in the other.

This is important to keep in mind, because the software industry, more than any other, has been responsible for reinforcing and solidifying this (erroneous) perspective. During the first generation of desktop application development, software solutions were built to automate the functions of traditional line and staff functions. This made a great deal of sense.

From a sales and revenue perspective, it is easier to sell a limited niche software “tool” to an established customer base that will ensure both quick acceptance and immediate realization of productivity and labor savings. The connection from the purchase to ROI was easily traceable in the time span and at the level of the person performing their workaday tasks.

Thus, solutions were built to satisfy the needs of cost analysts, schedule analysts, systems engineers, cost estimators, and others. Where specific solutions left gaps, such spreadsheet solutions such as Microsoft Excel were employed to fill them. It was in no one’s interest to go beyond their core competency. Once a dominant or set of dominant incumbents (a monoposony) inhabited a niche, they employed the usual strategies for “stickiness” to defend territory and raise barriers to new entries.

What was not anticipated by many organizations was the fact that once you automate a function that the nature of the system, if one is to implement the most effective organizational structure, is transformed to conform to the most efficient flow and use of data–and its resulting transformation into information and intelligence. Oftentimes the skill set to use the intelligence does not exist because the resulting insights and synergy involved in taking larger and more comprehensive datasets which themselves are more credible and accurate was not anticipated in adjusting the organizational structure.

This is changing and must change, because the old way of using limited sets of data in the age of big(ger) data that provide a more comprehensive view of business conditions is not tenable. At least, not if a company or organization wants to stay relevant or profitable.

Characteristics and Basic Elements of the Project Schedule

If one were to perform a Google search of project schedule while reading this post, you would find a number of definitions, some of which overlap. For example, the PMBOK defines a schedule as, quite simply, “the planned dates for performing activities and the planned dates for meeting milestones.”

Thus our elements include planned dates, activities, and milestones. But is that all? Under this definition, any kind of plan, from a minor household renovation or upgrade to building an aircraft carrier would contain only these elements.

I don’t think so.

For complex projects and programs, which is the focus on this blog, our definition of a project schedule is a bit more comprehensive. If you go to the aforementioned A Guide for DoD Program Managers mentioned in my last post, you will find even less specificity.

The reason for this is that what we define as a project schedule is part and parcel of the planning phase of a project, which is then further specified in the specific time-phased planning elements for execution of the project through its lifespan into production. It is the schedule that ties together all of the disciplines in putting together a project–acquisition, systems engineering, cost estimating, and project performance management.

In attending scheduled-focused conferences over the years and in talking to program management colleagues is the refrain that:

a. It is hard to find a good scheduler, and

b. Constructing a schedule is more of an art than a science.

I can only say that this cedes the field to a small cadre of personnel who perform an essential function, but who do so with few objective tests of effectiveness or accountability–until it is too late.

But the reality is quite different from the fuzzy perception of schedule that is often assumed. All critical path method (CPM) schedules describe the same phenomena, though the lexicon will vary based on the specific proprietary application employed.

In government-focused and large commercial projects, the schedule is heart of planning and execution. In the DoD world it is known as the Integrated Master Schedule (IMS), which utilize the inherent bottom-up relationships of elements to determine the critical path. The main sources regarding the IMS have a great deal of overlap, but tend to be either aspirational (and unfortunately not prescriptive in defining the basic characteristics of an IMS) or reflect the “art over science” approach. For those following along these are the DoD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide of 21 October 2005, the NAVAIR Integrated Master Schedule (IMS) Guidebook of February 2010, and the NDIA Planning and Scheduling Excellence Guide (PASEG) of 9 March 2016 (unfortunately no current direct link).

The key elements that comprise an IMS, in addition to what we identified under the PMBOK are that it is networked schedule consisting of specific durations that are assigned to specific work tasks that must be accomplished in discrete work packages. In most cases these durations will be derived by some kind of either fixed, manual method or through the inherent optimization algorithm being applied by the CPM application. More on this below. But these work packages are discrete, meaning that they represent the full scope of the work that must be accomplished to during the specified duration for the creation of an end product. Discrete work is distinguished from level of effort (LOE) work, the latter being effort that is always expended, such as administrative and management tasks, that are not directly tied to the accomplishment of an end product.

These work packages are tied together to illustrate antecedent and progressive work that show predecessor and successor relationships. Long term planning activities, which cannot be fleshed out until more immediate work is completed are set aside as placeholders called planning packages. Each of the elements that are tracked in the IMS are based on the presentation of established criteria that define completion, events, and specific accomplishments.

The most comprehensive IMSs consist of detailed planning that include resources and elements of cost.

Detailed Elements of the IMS

Given these general elements, the best source of identifying the key elements of detailed schedules is also found in Department of Defense documents. The core document in this case is the Data Item Description for the IMS numbered as DI-MGMT-81650. The latest one is dated March 30, 2005. There are a minimum of 32 data elements, some of these already mentioned and which I will not repeat in this post since they are pretty well listed and identified in the source document.

For those not familiar with these documents, Data Item Descriptions (or DiDs–gotta love acronyms) represent the detailed technical documents for artifacts involved in the management of DoD-related operations. Thus, this provides us with a pretty good inventory of elements to source. But there are others that are implied.

For example, the 81650 DiD identifies an element known as “methodology.” What this means is that each scheduling application has an optimization engine where the true differences in schedule construction and intellectual property reside. Elements that affect these calculations are time-based, duration-based, float, and slack, and those related to resources.

These time-based elements consist of early start, early finish, late start, late finish. Duration-based elements consist of shortest time, longest time, greatest rank weight. An additional element related to schedule float identifies minimum slack. Resources are further delineated by the greatest work content and the greatest cumulative resource content.

I would note that the NDIA PASEG adds some sub-elements to this list that are based on the algorithmic result of the schedule engines and, thus, tends to ignore the antecedent salient elements of validating the optimization engine found above. These additional sub-elements are total float, free float, soft constraints, hard constraints, and–also found in the aforementioned DiD–program, task, and resource calendars.

Normally, this is where a survey would end–with schedule-specific data elements focused on the details of the schedule. But we’re going to challenge our assumptions a bit more.

Framing Assumptions of Schedules and Programs

The essential document that provides a definition of the term “framing assumption” was published by RAND Corporation in 2014 entitled Identifying Acquisition Framing Assumptions Through Structured Deliberation by Mark V. Arena and Lauren A. Mayer.  The definition of a framing assumption is “any explicit or implicit assumption that is central is shaping cost, schedule, or performance expectations.”

As I have explored in my prior post, the use of the term “cost” is a fuzzy one. To some it means earned value management, which measures a small part of the costs of development and ownership of a system. To others it means total cost of ownership. Schedule is an implicit part of this definition, and then we have performance expectations, which I will deal with in a separate post.

But we can apply the concept of framing assumptions in two ways.

The first applies to the assumed purpose of the schedule. What do we construct one? This goes back to my earlier statement that “…the schedule…ties together all of the disciplines in putting together a project–acquisition, systems engineering, cost estimating, and project performance management.”

For the NDIA PASEG the IMS is a “tool, not just a report” that “provides an ever-changing window into the progress (or lack of it) of current work effort. The strategic mission of the schedule is to point out future risks and opportunities.”

For the NAVAIR IMS Guide the IMS “At a top level…contain(ing) the networked, detailed tasks necessary to ensure successful program execution…” that “capture(s) project tasks and task relationships”, “show(s) the magnitude and how long each task will take”, “show(s) resources, durations, and constraints for each task” and “show(s) the critical path.”

For the DiD 81650 “The Integrated Master Schedule (IMS) is an integrated schedule containing the networked, detailed tasks necessary to ensure successful program execution.”

But the most comprehensive definition that goes to the core of the purpose of an IMS can be found in paragraph 1.2 of the DoD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide (IMP/IMS Guide). The elements of this purpose is worth transcribing, because if we have a requirement and cannot ask the “So What?” question, that is, if we cannot effectively determine why something must be done, then it probably does not need to be done (or we need to apply rigor in the development our expertise).

For what the IMP/IMS Guide does is clearly tie the schedule to the programmatic framing assumptions (used in the context in which RAND meant it) from initial acquisition through planning. Thus, the Integrated Master Plan (IMP) is firmly established as an antecedent and intermediate planning process (not merely an artifact or tool), that results in the program R&D execution process.

Taken in whole these processes and the resulting artifacts of the processes provide:

a. Provides offerors and acquiring activities with detailed execution planning, organization, and scheduling information that sets realistic expectations for the resulting contract action.

b. Serves as the execution plan for how the supplier will meet the contract’s performance requirements within cost and schedule constraints.

c. Provides a basis for integrating all of the functions involved in development and deployment of the system being acquired and, after award, sets the framing assumptions of the program.

d. Provides the basis for determining and assessing progress, identifying risks, determining the basis for contractual award fees and penalties, assess progress on Key Performance Parameters (KPPs) and Technical Performance Measures (TPMs), determine alternative paths to project completion, and determine opportunities for innovation and new acquisitions not apparent at the time of the award.

What all of this means is that the Integrated Master Schedule is too important to be left to the master scheduler. Yes, the schedule is a “tool” to those at the most basic tactical level in work execution. Yes, it is also an artifact and record.

But, more importantly, it is the comprehensive notional representation of the project’s or program’s scope, effort, progress, and assessment.

Private and Government-focused Industry Practice

A word has to mentioned here about the difference in practice between purely private industry practice in managing large projects and programs, and the skewing in the posts that focus on those industries that focus on public sector acquisition.

In the listing of schedule elements listed earlier there is reference to resources and elements of cost, yet here is an area that standard practice diverges. In private industry the application of resource assignments to specific work is standard practice and found in the IMS.

In companies focused on the public sector and DoD, the practice is to establish a different set of data outside of the schedule to manage resources. Needless to say this creates problems of validation of data across disparate systems related to the lowest level of planning and execution of a project or program. The basis for it, I think, relates to viewing the schedule as a “tool” and not the basis for project execution. This “tool” mindset also allows for separate “earned value engines” that oftentimes do not synchronize with the execution of the schedule, not only undermining the practical value of both, but also creating systems complexity and inefficiency where none need exist.

Another gap found in many areas of public acquisition concerns the development of an integrated master plan antecedent to the integrated master schedule. The cause here, once again, I believe is viewing the discipline of systems engineering separate; one that is somehow walled off from the continuing assessment of program execution, though that assumption is not supported by program phasing and milestone planning and achievement.

From the perspective of Integrated Program/Project Management, these considerations cannot be ignored, and so our inventory of essential data elements must include elements from these practices.

But Wait! There’s More!

Most discussions at conferences and professional meetings will usually stop at this point–viewing cost and schedule integration as the essence of IPM–with “cost’ limited to EVM. Some will add some “oh by the ways” such as technical performance and risk. I will address these in the next post as well.

But there are also other systems and processes that are relevant to our inventory. But what I have covered thus far in this series should challenge you if you have been paying attention.

I tackled cost first because of the assumptions implicit in equating it with EVM, and then went on to demonstrate that there are other elements of cost that provide a more comprehensive view. This is not denigrate the value of EVM, since it is an essential process in project management, but to demonstrate that its analytics are not comprehensive and, as with any complex system, require the contribution of additional information, depending on the level and type of work performance and progress being recorded and assessed.

In this post I have tacked the IMS, and have demonstrated that it is not supplementary process, but central to all other processes and actions being taken in the execution of the project or program. Many times people enter the schedule from an assessment of cost performance–tracing cost drivers to specific schedule activities and then tasks. But this has it backwards, based on the best technology available sometime in the late 1990s.

It is the schedule that brings together all relevant information from our execution and control processes and systems. It seems to me that perhaps the first place one goes is the schedule, that the first element to trace are those related to schedule slippage and unexpected resource consumption, and then to trace these to contract cost impact.

But, of course, there is more–and these other elements may turn out to be of greater consequence than just cost and schedule considerations. More on these in my next post.

In Closing: Battle Rhythm and the Plans of the Day and Week

When I was on active duty in the Navy we planned our days and weeks around a Plan of the Day or Plan of the Week. This is a posted agenda so that the entire ship or command understands the major events that affect its operations. It establishes focus on the main events at hand and fosters communication both laterally and vertically within the chain of command.

As one rises in rank and responsibility it is important to understand the operational tempo of the unit or ship, its systems, and subsystems. This is important in avoiding crisis management.This is known as Battle Rhythm.

Baked into the schedule (assuming proper construction and effective integrated product teaming) are the major events, milestones, and expected achievement of the program or project. Thus, there are events that should be planned around and anticipation of these items on a daily, weekly, biweekly, monthly, quarterly, and major milestone basis.

Given an effective battle rhythm, a PM should never complain about performance and progress indicators “looking into the rear view mirror”. If that is the case then perhaps the PM should look at the effectiveness and timeliness of the underlying project and program systems.Thus, when a PMO complains of information and intelligence being too late to be actionable, it is actually describing a condition of ineffective, latent, and disjointed information and intelligence systems.

Thus, our next step in our next post is to identify more salient IPM elements that cut to the heart of the matter.