Back to School Daze Blogging–DCMA Investigation on POGO, DDSTOP, $600 Ashtrays,and Epistemic Sunk Costs

Family summer visits and trips are in the rear view–as well as the simultaneous demands of balancing the responsibilities of a, you know, day job–and so it is time to take up blogging once again.

I will return to my running topic of Integrated Program and Project Management in short order, but a topic of more immediate interest concerns the article that appeared on the website for pogo.org last week entitled “Pentagon’s Contracting Gurus Mismanaged Their Own Contracts.” Such provocative headlines are part and parcel of organizations like POGO, which have an agenda that seems to cross the line between reasonable concern and unhinged outrage with a tinge conspiracy mongering. But the content of the article itself is accurate and well written, if also somewhat ripe with overstatement, so I think it useful to unpack what it says and what it means.

POGO and Its Sources

The source of the article comes from three sources regarding an internal Defense Contract Management Agency (DCMA) IT project known as the Integrated Workflow Management System (IWMS). These consist of a September 2017 preliminary investigative report, an April 2018 internal memo, and a draft of the final report.

POGO begins the article by stating that DCMA administers over $5 trillion in contracts for the Department of Defense. The article erroneously asserts that it also negotiates these contracts, apparently not understanding the process of contract oversight and administration. The cost of IWMS was apparently $46.6M and the investigation into the management and administration of the program was initiated by the then-Commander of DCMA, Lieutenant General Wendy Masiello, shortly before she retired from the government in May 2017.

The implication here, given the headline, seems to be that if there is a problem in internal management within the agency, then that would translate into questioning its administration of the $5 trillion in contract value. I view it differently, given that I understand that there are separate lines of responsibility in the agency that do not overlap, particularly in IT. Of the $46.6M there is a question of whether $17M in value was properly funded. More on this below, but note that, to put things in perspective, $46.6M is .000932% of DCMA’s oversight responsibility. This is aside from the fact that the comparison is not quite correct, given that the CIO had his own budget, which was somewhat smaller and unrelated to the $5 trillion figure. But I think it important to note that POGO’s headline and the introduction of figures, while sounding authoritative, are irrelevant to the findings of the internal investigation and draft report. This is a scare story using scare numbers, particularly given the lack of context. I had some direct experience in my military career with issues inspired by the POGO’s founders’ agenda that I will cover below.

In addition to the internal investigation on IWMS, there was also an inspector general (IG) investigation of thirteen IT services contracts that resulted in what can only be described as pedestrian procedural discrepancies that are easily correctable, despite the typically overblown language found in most IG reports. Thus, I will concentrate on this post on the more serious findings of the internal investigation.

My Own Experience with DCMA

A note at this point on full disclosure: I have done business with and continue to do business with DCMA, both as a paid supplier of software solutions, and have interacted with DCMA personnel at publicly attended professional forums and workshops. I have no direct connection, as far as I am aware, to the IWMS program, though given that the assessment is to the IT organization, it is possible that there was an indirect relationship. I have met Lieutenant General Masiello and dealt with some of her subordinates not only during her time at DCMA, but also in some of her previous assignments in Air Force. I always found her to be an honest and diligent officer and respect her judgment. Her distinguished career speaks for itself. I have talked on the telephone to some of the individuals mentioned in the article on unrelated matters, and was aware of their oversight of some of my own efforts. My familiarity with all of them was both businesslike and brief.

As a supplier to DCMA my own contracts and the personnel that administer them were, from time-to-time, affected by the fallout from what I now know to have occurred. Rumors have swirled in our industry regarding the alleged mismanagement of an IT program in DCMA, but until the POGO article, the reasons for things such as a temporary freeze and review of existing IT programs and other actions were viewed as part and parcel of managing a large organization. I guess the explanation is now clear.

The Findings of the Investigation

The issue at hand is largely surrounding the method of source selection, which may have constituted a conflict of interest, and the type of money that was used to fund the program. In reading the report I was reminded of what Glen Alleman recently wrote in his blog entitled “DDSTOP: The Saga Continues.” The acronym DDSTOP means: Don’t Do Stupid Things On Purpose.

There is actually an economic behavioral principle for DDSTOP that explains why people make and double down on bad decisions and irrational beliefs. It is called epistemic sunk cost. It is what causes people to double down in gambling (to the great benefit of the house), to persist in mistaken beliefs, and, as stated in the link above, to “persist with the option which they have already invested in and resist changing to another option that might be more suitable regarding the future requirements of the situation.” The findings seem to document a situation that fits this last description.

In going over the findings of the report, it appears that IWMS’s program violated the following:

a. Contractual efforts in the program that were appropriate for the use of Research, Development, Test and Evaluation (R,D,T & E) funds as opposed to those appropriate for O&M (Operations and Maintenance) funds. What the U.S. Department of Defense calls “color of money.”

b. Amounts that were expended on contract that exceeded the authorized funding documents, which is largely based on the findings regarding the appropriate color of money. This would constitute a serious violation known as an Anti-Deficiency Act violation which, in layman’s terms, is directed to punish public employees for the misappropriation of government funds.

c. Expended amounts of O&M that exceeded the authorized levels.

d. Poor or non-existent program management and cost performance management.

e. Inappropriate contracting vehicles that, taken together, sidestepped more stringent oversight, aside from the award of a software solutions contract to the same company that defined the agency’s requirements.

Some of these are procedural and some are serious, particularly the Anti-deficiency Act (ADA) violations, are serious. In the Contracting Officer’s rulebook, you can withstand pedestrian procedural and administrative findings that are part and parcel of running an intensive contracting organization that acquires a multitude of supplies and services under deadline. But an ADA violation is the deadly one, since it is a violation of statute.

As a result of these findings, the recommendation is for DCMA to lose acquisition authority over the DoD micro-contracting level ($10,000). Organizationally and procedurally, this is a significant and mission-disruptive recommendation.

The Role and Importance of DCMA

DCMA performs an important role in contract compliance and oversight to ensure that public monies are spent properly and for the intended purpose. They perform this role mostly on contracts that are negotiated and entered into by other agencies and the military services within the Department of Defense, where they are assigned contract administration duties. Thus, the fact that DCMA’s internal IT acquisition systems and procedures were problematic is embarrassing.

But some perspective is necessary because there is a drive by some more extreme elements in Congress and elsewhere that would like to see the elimination of the agency. I believe that this would be a grave mistake. As John F. Kennedy is quoted as having said: “You don’t tear your fences down unless you know why they were put up.”

For those of you who were not around prior to the formation of DCMA or its predecessor organization, the Defense Contract Management Command (DCMC), it is important to note that the formation of the agency is a result of acquisition reform. Prior to 1989 the contract administration services (CAS) capabilities of the military services and various DoD offices varied greatly in capability, experience, and oversight effectiveness.Some of these duties had been assigned to what is now the Defense Logistics Agency (DLA), but major acquisition contracts remained with the Services.

For example, when I was on active duty as a young Navy Supply Corps Officer as part of the first class that was to be the Navy Acquisition Corps, I was taught cradle-to-grave contracting. That is, I learned to perform customer requirements development, economic analysis, contract planning, development of a negotiating position, contract negotiation, and contract administration–soup to nuts. The expense involved in developing and maintaining the skill set required of personnel to maintain such a broad-based expertise is unsustainable. For analogy, it is as if every member of a baseball club must be able to play all nine positions at the same level of expertise; it is impossible.

Furthermore, for contract administration a defense contractor would have contractual obligations for oversight in San Diego, where I was stationed, that were different from contracts awarded in Long Beach or Norfolk or any of the other locations where a contracting office was located. Furthermore, the military services, having their own organizational cultures, provided additional variations that created a plethora of unique requirements that added cost, duplication, inconsistency, and inter-organizational conflict.

This assertion is more than anecdotal. A series of studies were commissioned in the 1980s (the findings of which were subsequently affirmed) to eliminate duplication and inconsistency in the administration of contracts, particularly major acquisition programs. Thus, DCMC was first established under DLA and subsequently became its own agency. Having inherited many of the contracting field office, the agency has struggled to consolidate operations so that CAS is administered in a consistent manner across contracts. Because contract negotiation and program management still resides in the military services, there is a natural point of conflict between the services and the agency.

In my view, this conflict is a healthy one, as all power in the hands of a single individual, such as a program manager, would lead to more fraud, waste, and abuse, not less. Internal checks and balances are necessary in proper public administration, where some efficiency is sacrificed to accountability. It is not just the goal of government to “make the trains run on time”, but to perform oversight of the public’s money so that there is accountability in its expenditure, and integrity in systems and procedures. In the case of CAS, it is to ensure that what is being procured actually gets delivered in conformance to the contract terms and conditions designed to reduce the inherent risk in complex acquisition programs.

In order to do its job effectively, DCMA requires innovative digital systems to allow it to perform its CAS function. As a result, the agency must also possess an acquisition capability. Given the size of the task at hand in performing CAS on over $5 trillion of contract effort, the data involved is quite large, and the number of personnel geographically distributed. The inevitable comparisons to private industry will arise, but few companies in the world have to perform this level of oversight on such a large economic scale, which includes contracts comprising every major supplier to the U.S. Department of Defense, involving detailed knowledge of the management control systems of those companies that receive the taxpayer’s money. Thus, this is a uniquely difficult job. When one understands that in private industry the standard failure rate of IT projects is more than 70% percent, then one cannot help but be unimpressed by these findings, given the challenge.

Assessing the Findings and Recommendations

There is a reason why internal oversight documents of this sort stay confidential–it is because these are preliminary/draft findings and there are two sides to every story which may lead to revisions. In addition, reading these findings without the appropriate supporting documentation can lead one to the wrong impression and conclusions. But it is important to note that this was an internally generated investigation. The checks and balances of management oversight that should occur, did occur. But let’s take a close look at what the reports indicate so that we can draw some lessons. I also need to mention here that POGO’s conflation of the specific issues in this program as a “poster child” for cost overruns and schedule slippage displays a vast ignorance of DoD procurement systems on the part of the article’s author.

Money, Money, Money

The core issue in the findings revolves around the proper color of money, which seems to hinge on the definition of Commercial-Off-The-Shelf (COTS) software and the effort that was expended using the two main types of money that apply to the core contract: RDT&E and O&M.

Let’s take the last point first. It appears that the IWMS effort consisted of a combination of COTS and custom software. This would require acquisition, software familiarization, and development work. It appears that the CIO was essentially running a proof-of-concept to see what would work, and then incrementally transitioned to developing the solution.

What is interesting is that there is currently an initiative in the Department of Defense to do exactly what the DCMA CIO did as part of his own initiative in introducing a new technological approach to create IWMS. It is called Other Transactional Authority (OTA). The concept didn’t exist and was not authorized until the 2016 NDAA and is given specific statutory authority under 10 U.S.C. 2371b. This doesn’t excuse the actions that led to the findings, but it is interesting that the CIO, in taking an incremental approach to finding a solution, also did exactly what was recommended in the 2016 GAO report that POGO references in their article.

Furthermore, as a career Navy Supply Corps Officer, I have often gotten into esoteric discussions in contracts regarding the proper color of money. Despite the assertion of the investigation, there is a lot of room for interpretation in the DoD guidance, not to mention a stark contrast in interpreting the proper role of RDT&E and O&M in the procurement of business software solutions.

When I was on the NAVAIR staff and at OSD I ran into the difference in military service culture where what Air Force financial managers often specified for RDT&E would never be approved by Navy financial managers where, in the latter case, they specified that only O&M dollars applied, despite whether development took place. Given that there was an Air Force flavor to the internal investigation, I would be interested to know whether the opinion of the investigators in making an ADA determination would withstand objective scrutiny among a panel of government comptrollers.

I am certain that, given the differing mix of military and civil service cultures at DCMA–and the mixed colors of money that applied to the effort–that the legal review that was sought to resolve the issue. One of the principles of law is that when you rely upon legal advice to take an action that you have a defense, unless your state of mind and the corollary actions that you took indicates that you manipulated the system to obtain a result that shows that you intended to violate the law. I just do not see that here, based on what has been presented in the materials.

It is very well possible that an inadvertent ADA violation occurred by default because of an improper interpretation of the use of the monies involved. This does not rise to the level of a scandal. But going back to the confusion that I have faced from my own experiences on active duty, I certainly hope that this investigation is not used as a precedent to review all contracts under the approach of accepting a post-hoc alternative interpretation by another individual who just happens to be an inspector long after a reasonable legal determination was made, regardless of how erroneous the new expert finds the opinion. This is not an argument against accountability, but absent corruption or criminal intent, a legal finding is a valid defense and should stand as the final determination for that case.

In addition, this interpretation of RDT&E vs. O&M relies upon an interpretation of COTS. I daresay that even those who throw that term around and who are familiar with the FAR fully understand what constitutes COTS when the line between adaptability and point solutions is being blurred by new technology.

Where the criticism is very much warranted are those areas where the budget authority would have been exceeded in any event–and it is here that the ADA determination is most damning. It is one thing to disagree on the color of money that applies to different contract line items, but it is another to completely lack financial control.

Part of the reason for lack of financial control was the absence of good contracting practices and the imposition of program management.

Contracts 101

While I note that the CIO took an incremental approach to IWMS–what a prudent manager would seem to do–what was lacking was a cohesive vision and a well-informed culture of compliance to acquisition policy that would avoid even the appearance of impropriety and favoritism. Under the OTA authority that I reference above as a new aspect of acquisition reform, the successful implementation of a proof-of-concept does not guarantee the incumbent provider continued business–salient characteristics for the solution are publicized and the opportunity advertised under free and open competition.

After all, everyone has their favorite applications and, even inadvertently, an individual can act improperly because of selection bias. The procurement procedures are established to prevent abuse and favoritism. As a solution provider I have fumed quite often where a selection was made without competition based on market surveys or use of a non-mandatory GSA contract, which usually turn out to be a smokescreen for pre-selection.

There are two areas of fault on IMWS from the perspective of acquisition practice, and another in relation to program management.

These are the initial selection of Apprio, which had laid out the initial requirements and subsequently failed to have the required integration functionality, and then, the selection of Discover Technologies under a non-mandatory GSA Blanket Purchase Agreement (BPA) contract under a sole source action. Furthermore, the contract type was not appropriate to the task at hand, and the arbitrary selection of Discover precluded the agency finding a better solution more fit to its needs.

The use of the GSA BPA allowed managers, however, to essentially spit the requirements to stay below more stringent management guidelines–an obvious violation of acquisition regulation that will get you removed from your position. This leads us to what I think is the root cause of all of these clearly avoidable errors in judgment.

Program Management 101

Personnel in the agency familiar with the requirements to replace the aging procurement management system understood from the outset that the total cost would probably fall somewhere between $20M and $40M. Yet all effort was made to reduce the risk by splitting requirements and failing to apply a programmatic approach to a clearly complex undertaking.

This would have required the agency to take the steps to establish an acquisition strategy, open the requirement based on a clear performance work statement to free and open competition, and then to establish a program management office to manage the effort and to allow oversight of progress and assessment of risks in a formalized environment.

The establishment of a program management organization would have prevented the lack of financial control, and would have put in place sufficient oversight by senior management to ensure progress and achievement of organizational goals. In a word, a good deal of the decision-making was based on doing stupid things on purpose.

The Recommendations

In reviewing the recommendations of the internal investigation, I think my own personal involvement in a very similar issue from 1985 will establish a baseline for comparison.

As I indicated earlier, in the early 1980s, as a young Navy commissioned officer, I was part of the first class of what was to be the Navy Acquisition Corps, stationed at the Supply Center in San Diego, California. I had served as a contracting intern and, after extensive education through the University of Virginia Darden School of Business, the extended Federal Acquisition Regulation (FAR) courses that were given at the time at Fort Lee, Virginia, and coursework provided by other federal acquisition organizations and colleges, I attained my warrant as a contracting officer. I also worked on acquisition reform issues, some of which were eventually adopted by the Navy and DoD.

During this time NAS Miramar was the home of Top Gun. In 1984 Congressman Duncan Hunter (the elder not the currently indicted junior of the same name, though from the same San Diego district), inspired by news of $7,600 coffee maker and a $435 hammer publicized by the founders of POGO, was given documents by a disgruntled employee at the base regarding the acquisition of replacement E-2C ashtrays that had a cost of $300. He presented them to the Base Commander, which launched an investigation.

I served on the JAG investigation under the authority of the Wing Commander regarding the acquisitions and then, upon the firing of virtually the entire chain of command at NAS Miramar, which included the Wing Commander himself, became the Officer-in-Charge of Supply Center San Diego Detachment NAS Miramar. Under Navy Secretary Lehman’s direction I was charged with determining the root cause of the acquisition abuses and given 60-90 days to take immediate corrective action and clear all possible discrepancies.

I am not certain who initiated the firings of the chain of command. From talking with contemporaneous senior personnel at the time it appeared to have been instigated in a fit of pique by the sometimes volcanic Secretary of Defense Caspar Weinberger. While I am sure that Secretary Weinberger experienced some emotional release through that action, placed in perspective, his blanket firing of the chain of command, in my opinion, was poorly advised and counterproductive. It was also grossly unfair, given what my team and I found as the root cause.

First of all, the ashtray was misrepresented in the press as a $600 ashtray because during the JAG I had sent a sample ashtray to the Navy industrial activity at North Island with a request to tell me what the fabrication of one ashtray would cost and to provide the industrial production curve that would reduce the unit price to a reasonable level. The figure of $600 was to fabricate one. A “whistleblower” at North Island took this slice of information out of context and leaked it to the press. So the $300 ashtray, which was bad enough, became the $600 ashtray.

Second, the disgruntled employee who gave the files to Congressman Hunter had been laterally assigned out of her position as a contracting officer by the Supply Officer because of the very reason that the pricing of the ashtray was not reasonable, among other unsatisfactory performance measures that indicated that she was not fit to perform those duties.

Third, there was a systemic issue in the acquisition of odd parts. For some reason there was an ashtray in the cockpit of the E-2C. These aircraft were able to stay in the air an extended period of time. A pilot had actually decided to light up during a local mission and, his attention diverted, lost control of the aircraft and crashed. Secretary Lehman ordered corrective action. The corrective action taken by the squadron at NAS Miramar was to remove the ashtray from the cockpit and store them in a hangar locker.

Four, there was an issue of fraud. During inspection the spare ashtrays were removed and deposited in the scrap metal dumpster on base. The tech rep for the DoD supplier on base retrieved the ashtrays and sold them back to the government for the price to fabricate one, given that the supply system had not experienced enough demand to keep them in stock.

Fifth, back to the systemic issue. When an aircraft is to be readied for deployment there can be no holes representing missing items in the cockpit. A deploying aircraft with this condition is then grounded and a high priority “casuality report” or CASREP is generated. The CASREP was referred to purchasing which then paid $300 for each ashtray. The contracting officer, however, feeling under pressure by the high priority requisition, did not do due diligence in questioning the supplier on the cost of the ashtray. In addition, given that several aircraft deploy, there were a number of these requisitions that should have led the contracting officer to look into the matter more closely to determine price reasonableness.

Furthermore, I found that buying personnel were not properly trained, that systems and procedures were not established or enforced, that the knowledge of the FAR was spotty, and that procurements did not go through multiple stages of review to ensure compliance with acquisition law, proper documentation, and administrative procedure.

Note that in the end this “scandal” was born by a combination of systemic issues, poor decision-making, lack of training, employee discontent, and incompetence.

I successfully corrected the issues at NAS Miramar during the prescribed time set by the Secretary of the Navy, worked with the media to instill public confidence in the system, built up morale, established better customer service, reduced procurement acquisition lead times (PALT), recommended necessary disciplinary action where it seemed appropriate, particularly in relation to the problematic employee, recovered monies from the supplier, referred the fraud issues to Navy legal, and turned over duties to a new chain of command.

NAS Miramar procurement continued to do its necessary job and is still there.

What the higher chain of command did not do was to take away the procurement authority of NAS Miramar. It did not eliminate or reduce the organization. It did not close NAS Miramar.

It requires leadership and focus to take effective corrective action to not only fix a broken system, but to make it better while the corrective actions are being taken. As I outlined above, DCMA performs an essential mission. As it transitions to a data-driven approach and works to reduce redundancy and inefficiency in its systems, it will require more powerful technologies to support its CAS function, and the ability to acquire those technologies to support that function.

Walk This Way — DoD IG Reviews DCMA Contracting Officer Business Systems Deficiencies

The sufficiency and effectiveness of business systems is an essential element in the project management ecosystem.  Far beyond performance measurement of the actual effort, the sufficiency of the business systems to support the effort are essential in its success.  If the systems in place do not properly track and record the transactions behind the work being performed, the credibility of the data is called into question.  Furthermore, support and logistical systems, such as procurement, supply, and material management, contribute in a very real way, to work accomplishment.  If that spare part isn’t in-house on time, the work stops.

In catching up on reading this month, I found that the DoD Inspector General issued a report on October 1 showing that of 21 audits demonstrating business system deficiencies, contracting officer timeliness in meeting DFARS deadlines at various milestones existed in every case.  For example, in 17 of those cases Contracting Officers did not issue final determination letters within 30 days of the report as required by the DFARS.  In eight cases required withholds were not assessed.

For those of you who are unfamiliar with the six business systems assessed under DoD contractor project management, they consist of accounting, estimating, material management, purchasing, earned value management, and government property.  The greater the credibility and fidelity of these systems, the greater level of confidence that the government can have in ensuring that the data received in reporting on execution of public funds under these contracts.

To a certain extent the deadlines under the DFARS are so tightly scheduled that they fail to take into account normal delays in operations.  Forbid that the Contracting Officer may be on leave when the audit is received or is engaged in other detailed negotiations.  In recent years the contracting specialty within the government, like government in general, has been seriously understaffed, underfunded, and unsupported.  Given that oftentimes the best and the brightest soon leave government service for greener pastures in the private sector, what is often left are inexperienced and overworked (though mostly dedicated) personnel who do not have the skills or the time to engage in systems thinking in approaching noted deficiencies in these systems.

This pressure for staff reduction, even in areas that have been decimated by austerity politics, is significant.  In the report I could not help but shake my head when an Excel spreadsheet was identified as the “Contractor Business System Determination Timeline Tracking Tool.”  This reminds me of my initial assignment as a young Navy officer and my first assignment as a contract negotiator where I also performed collateral duties in building simple automated tools.  (This led to me being assigned later as the program manager of the first Navy contract and purchase order management system.) That very first system that I built, however, was tracking contract milestone deadlines.  It was done in VisiCalc and the year was 1984.

That a major procurement agency of the U.S. Department of Defense is still using a simple and ineffective spreadsheet tracking “tool” more than 30 years after my own experience is both depressing and alarming.  There is a long and winding history on why they would find themselves in this condition, but some additional training, which was the agency’s response to the IG, is not going to solve the problem.  In fact, such an approach is so ineffective it’s not even a Band-Aid.  It’s a bureaucratic function of answering the mail.

The reason why it won’t solve the problem is because there is no magic wand to get those additional contract negotiators and contracting officers in place.  The large intern program of recruiting young people from colleges to grow talent and provide people with a promising career track is long gone.  Interdisciplinary and cross-domain expertise required in today’s world to reflect the new realities when procuring products and services are not in the works.  In places where they are being attempted, outmoded personnel classification systems based on older concepts of division of labor stand in the way.

The list of systemic causes could go on, but in the end it’s not in the DCMA response because no one cares, and if they do care, they can’t do anything about it.  It’s not as if “BEST TALENT LEAVES DUE TO PUBLIC HOSTILITY TO PUBLIC SERVICE”  was a headline of any significance.  The Post under Bezos is not going to run that one anytime soon, though we’ve been living under it since 1981.  The old “thank you for your service” line for veterans has become a joke.  Those who use this line might as well say what that really means, which is: “I’m glad it was you and not me.”

The only realistic way to augment an organization in this state in order the break the cycle is to automate the system–and to do it in a way as to tie together the entire system.  When I run into my consulting friends and colleagues and they repeat the mantra: “software doesn’t matter, it’s all based on systems” I can only shake my head.  I have learned to be more tactful.

In today’s world software matters.  Try doing today what we used to do with slide rules, scientific calculators, and process charts absent software.  Compare organizations that use the old division-of-labor, “best of breed” tool concept against those who have integrated their systems and use data across domains effectively.  Now tell me again why “software doesn’t matter.”  Not only does it matter but “software” isn’t all the same.  Some “software” consists of individual apps that do one thing.  Some “software” is designed to address enterprise challenges.  Some “software” is designed not only to enterprise challenges, but also to address the maximization of value in enterprise data.

In the case of procurement and business systems assessment, the only path forward for the agency will be to apply data-driven measures to the underlying systems and tie those assessments into a systemic solution that includes the contracting officers, negotiators, administrators, contracting officer representatives, the auditors, analysts, and management.  One can see, just in writing one line, how much more complex are the requirements for the automated panacea to replace “Contractor Business System Determination Timeline Tracking Tool.”  Is there any question why the “tool” is ineffective?

If this were the 1990s, though the practice still persists, we would sit down, perform systems analysis, outline the systems and subsystem solutions, and then through various stages of project management, design the software system to reflect the actual system in place as if organizational change did not exist.  This is the process that has a 90% failure rate across government and industry.  The level of denial to this figure is so great that I run into IT managers and CIOs every day that fail to know it or, if they do, believe that it will apply to them–and these are brilliant people.  It is selection bias and optimism, with a little (or a lot) of narcissism, run amok.  The physics and math on this are so well documented that you might as well take your organization’s money and go to Vegas with it.  Your local bookie could give you better odds.

The key is risk handling (not the weasel word “management,” not “mitigation” since some risks must simply be accepted, and certainly not the unrealistic term “avoidance”), and the deployment of technology that provides at least a partial solution to the entire problem, augmented by incremental changes to incorporate each system into the overall solution. For example, DeLong and Froomkin’s seminal paper on what they called “The Next Economy” holds true today.  The lack of transparency in software technologies requires a process whereby the market is surveyed, vendors must go through a series of assessments and demonstration tests, and where the selected technology then goes through stage gates: proof-of-concept, pilot, and, eventually deployment.  Success at each level gets rewarded with proceeding to the next step.

Thus, ideally the process includes introducing into the underlying functionality the specific functionality required by the organization through Agile processes where releasable versions of the solution are delivered at the end of each sprint.  One need not be an Agile Cultist to do this.  In my previous post I referred to Neil Killick’s simple checklist for whether you are engaged in Agile.  It is the best and most succinct distillation of both the process and value inherent in Agile that I have found to date, with all of the “woo-woo” taken out.  For an agency as Byzantine as DCMA, this is really the only realistic and effective approach.

DCMA is an essential agency in DoD acquisition management, but it cannot do what it once did under a more favorable funding environment.  To be frank, it didn’t even do its job all that well when a more favorable condition was in place, though things were better.  But this is also a factor in why it finds itself in its current state.  It was punished for its transgressions, perhaps too much.  Several waves of personnel cuts, staff reductions, and domain and corporate knowledge loss on top of the general trend has created an agency in a condition of siege.  As with any organization under siege, backbiting and careerism for those few remaining is rewarded.  Iconoclasts and thought leaders stay for a while before being driven away.  They are seen as being too risky.

This does not create a condition for an agency ready to accept or quickly execute change through new technology.  What it does do is allow portions of the agency to engage in cargo cult change management.  That is, it has the appearance of change but keeps self-interest comfortable and change in its place.  Over time–several years–with the few remaining resources committed to this process, they will work the “change.”  Eventually, they may even get something tangible, though suboptimized to conform to rice bowls; preferably after management has their retirement plans secured.

Still, the reality is that DCMA must be made to do it’s job because it is in the best interests of the U.S. Department of Defense.  The panacea will not be found through “collaboration” with industry, which consists of the companies which DCMA is tasked with overseeing and regulating.  We all know how well deregulation and collaboration has worked in the financial derivatives, banking, mortgage, and stock markets.  Nor will it come from organic efforts within an understaffed and under-resourced agency that will be unable to leverage the best and latest technology solutions under the unforgiving math of organic IT failure rates.  Nor will deploying the long outmoded approach of deploying suboptimized “tools” to address a particular problem.  The proper solution is to leverage effective COTS solutions that facilitate the challenge of systems integration and thinking.

 

 

I Heard It Through the Grapevine — Self Certification of Business Systems

Despite the best of intentions web blogging this week has been sparse, my time filled with contract negotiations and responses to solicitations.  Most recently on my radar is the latest proposed DFARS rule to allow contractors to self-certify their business systems.  Paul Cederwall at Pacific Northwest Government Contracting Update blog has has a lot to say about the rule that is interesting but he gets some important things wrong.

To provide a little background, a DFARS requirement that has been in place since May 18, 2011 established six business systems that must demonstrate accountability and traceability in their internal systems to ensure that there is a high degree of confidence in the integrity of the underlying systems of the contractor receiving award of a government contract.  You can find the language here.  Given that this is the taxpayer’s money, while there was a lot of fear and loathing on how the rule would be applied since it included some teeth–the threat of a withhold on payments–most individuals involved in acquisition reform welcomed it as a means of handling risk given that one of the elements of making an award is “responsibility.”  (This is one leg of the “three-legged stool test” that must be passed prior to a contracting officer making an award, the others being responsiveness, and price and price-related factors.  This last could include value determinations.)

The concept of responsibility is a loaded one, calling on the contracting officer to apply judgment, business knowledge and acumen, and analytical knowledge.  The elements, from the Corporate Findlaw site has a very good summary as follows:

“the FAR requires a prospective contractor to (1) have adequate financial resources to perform the contract; (2) be able to comply with the required or proposed delivery or performance schedule; (3) have a satisfactory performance record; (4) have a satisfactory record of integrity and business ethics; (5) have the necessary organization, experience, accounting and operational controls, and technical skills; (6) have the necessary production, construction, and technical equipment and facilities; and (7) be otherwise qualified and eligible to receive an award under applicable laws and regulations.”

Our acquisition systems, especially in regard to extremely large contracts that will turn into the complex projects that I write about here, tend to be pulled in many directions.  The customer, for example, wants what they need and to reduce the procurement lead time as much as possible.  Those who are given oversight responsibility and concern themselves with financial accountability focus on the need for compliance and integrity in the system, and to ensure that funds are being expended for the purpose contracted and in a manner that will lead to the contractually mandated outcome.  The contractors within the competitive range not only bid to win but their proposals are calibrated to take into account considerations of risk, market share and exposure, strategic positioning, and margin.

Thus, the Six Business Systems rule is a way of meeting the legal requirement of determining responsibility, which is part of the contracting officer’s charter, particularly under the real-world conditions imposed by governmental austerity.  But here is the rub.  When I was an active duty Navy contracting officer we had a great deal of resources at our disposal to ensure that we had done our due diligence prior to award.  The military services and the Department of Defense provided auditing resources to ensure the integrity of financial systems, expose rates during the negotiating process to meet the standard of “fair and reasonable,” and to ensure contract compliance and establish reliable reporting of progress based on those audits.

But things have changed and not always for the better.  During the 1980s and after technology was the first agent for change.  As a matter of fact I was the second project manager of the Navy Procurement System project in San Diego during that time and so was there at the beginning.  The people around me were prescient–despite the remonstrations to the contrary–that such digitization of procurement processes would result not only in improvements in the quality of information and productivity, but also reductions in workforce.  The result was that the federal government lost a great deal of corporate knowledge and wisdom while attempting to weed out suspected Luddites.  Hand-in-hand with this technological development came the rise of government austerity, which has become more, not less, severe over the last thirty years.  Thus the public lost more corporate knowledge and wisdom in the areas most sensitive to such losses.

Over this time criticism of the procurement system has seemed like the easiest horse of convenience to beat, especially in the environment of Washington, D.C.  The contracting officer pool is largely inexperienced.  The most experienced, if they last, are largely overworked, which diminishes effectiveness.  New hires are few and far between, especially given hiring and pay freezes.  Internships and mentoring programs that used to compete with the best of private industry have largely disappeared and most training budgets are either non-existent or bare-boned.  The expected procurement “scandals,” the overwhelming majority of which can be directly traced to the conditions described above as opposed to corruption, fraud, waste, or abuse, resulted.

Because of these conditions, the reaction in terms of ensuring integrity within the systems in lieu of finding scapegoats, was to first establish the Business Systems rule, which is in the best tradition of management.  But, given that things became unexpectedly more austere with government shutdowns and sequestration, the agency tasked with enforcing the rule–the Defense Contract Audit Agency (DCAA)–does not have the resources to complete a full review of the systems of the significant number of contractors that provide supplies and services to the U.S. Department of Defense.  Thus, the latest solution was to propose self-certification–one which was also sought by a good many companies in the industry.

There are criticisms coming from two different perspectives on the rule.  The first is that self-certification is charging the fox with watching the hen house.  The 2006-07 housing bubble and resulting banking crisis is an object lesson of insufficient oversight.

The other criticism comes from many in the industry that sought the change.  The rub here is that teeth were imposed in the process, requiring an annual independent CPA audit.  DCAA will review the results of the audit and the methodology used to make the determination of the certification.  This is where I part with PNWC.  The knee-jerk reaction is to question DCAA’s ability to judge whether the audit was completed properly because, after all, they were not “competent” to complete the audits to begin with.  This is a tautology and not a very good one.

As a leader and manager, if I delegate a task (given that I am usually busy on more pressing issues) and put checks and balances in place in the performance of that task, there will still come the time when I want that individual (or individuals) to present me with an accounting of what they did in the performance of that task.  This is called leadership and management.

The legal responsibility of DCAA in this case in their oversight role is to ensure the integrity of the contractor’s systems so that contracting officers can make awards with confidence to responsible firms.  DCAA is also accountable for the judgment and process in providing that certification.  One can delegate responsibility in the completion of a task but one cannot delegate accountability.

 