Back to School Daze Blogging–DCMA Investigation on POGO, DDSTOP, $600 Ashtrays,and Epistemic Sunk Costs

Family summer visits and trips are in the rear view–as well as the simultaneous demands of balancing the responsibilities of a, you know, day job–and so it is time to take up blogging once again.

I will return to my running topic of Integrated Program and Project Management in short order, but a topic of more immediate interest concerns the article that appeared on the website for pogo.org last week entitled “Pentagon’s Contracting Gurus Mismanaged Their Own Contracts.” Such provocative headlines are part and parcel of organizations like POGO, which have an agenda that seems to cross the line between reasonable concern and unhinged outrage with a tinge conspiracy mongering. But the content of the article itself is accurate and well written, if also somewhat ripe with overstatement, so I think it useful to unpack what it says and what it means.

POGO and Its Sources

The source of the article comes from three sources regarding an internal Defense Contract Management Agency (DCMA) IT project known as the Integrated Workflow Management System (IWMS). These consist of a September 2017 preliminary investigative report, an April 2018 internal memo, and a draft of the final report.

POGO begins the article by stating that DCMA administers over $5 trillion in contracts for the Department of Defense. The article erroneously asserts that it also negotiates these contracts, apparently not understanding the process of contract oversight and administration. The cost of IWMS was apparently $46.6M and the investigation into the management and administration of the program was initiated by the then-Commander of DCMA, Lieutenant General Wendy Masiello, shortly before she retired from the government in May 2017.

The implication here, given the headline, seems to be that if there is a problem in internal management within the agency, then that would translate into questioning its administration of the $5 trillion in contract value. I view it differently, given that I understand that there are separate lines of responsibility in the agency that do not overlap, particularly in IT. Of the $46.6M there is a question of whether $17M in value was properly funded. More on this below, but note that, to put things in perspective, $46.6M is .000932% of DCMA’s oversight responsibility. This is aside from the fact that the comparison is not quite correct, given that the CIO had his own budget, which was somewhat smaller and unrelated to the $5 trillion figure. But I think it important to note that POGO’s headline and the introduction of figures, while sounding authoritative, are irrelevant to the findings of the internal investigation and draft report. This is a scare story using scare numbers, particularly given the lack of context. I had some direct experience in my military career with issues inspired by the POGO’s founders’ agenda that I will cover below.

In addition to the internal investigation on IWMS, there was also an inspector general (IG) investigation of thirteen IT services contracts that resulted in what can only be described as pedestrian procedural discrepancies that are easily correctable, despite the typically overblown language found in most IG reports. Thus, I will concentrate on this post on the more serious findings of the internal investigation.

My Own Experience with DCMA

A note at this point on full disclosure: I have done business with and continue to do business with DCMA, both as a paid supplier of software solutions, and have interacted with DCMA personnel at publicly attended professional forums and workshops. I have no direct connection, as far as I am aware, to the IWMS program, though given that the assessment is to the IT organization, it is possible that there was an indirect relationship. I have met Lieutenant General Masiello and dealt with some of her subordinates not only during her time at DCMA, but also in some of her previous assignments in Air Force. I always found her to be an honest and diligent officer and respect her judgment. Her distinguished career speaks for itself. I have talked on the telephone to some of the individuals mentioned in the article on unrelated matters, and was aware of their oversight of some of my own efforts. My familiarity with all of them was both businesslike and brief.

As a supplier to DCMA my own contracts and the personnel that administer them were, from time-to-time, affected by the fallout from what I now know to have occurred. Rumors have swirled in our industry regarding the alleged mismanagement of an IT program in DCMA, but until the POGO article, the reasons for things such as a temporary freeze and review of existing IT programs and other actions were viewed as part and parcel of managing a large organization. I guess the explanation is now clear.

The Findings of the Investigation

The issue at hand is largely surrounding the method of source selection, which may have constituted a conflict of interest, and the type of money that was used to fund the program. In reading the report I was reminded of what Glen Alleman recently wrote in his blog entitled “DDSTOP: The Saga Continues.” The acronym DDSTOP means: Don’t Do Stupid Things On Purpose.

There is actually an economic behavioral principle for DDSTOP that explains why people make and double down on bad decisions and irrational beliefs. It is called epistemic sunk cost. It is what causes people to double down in gambling (to the great benefit of the house), to persist in mistaken beliefs, and, as stated in the link above, to “persist with the option which they have already invested in and resist changing to another option that might be more suitable regarding the future requirements of the situation.” The findings seem to document a situation that fits this last description.

In going over the findings of the report, it appears that IWMS’s program violated the following:

a. Contractual efforts in the program that were appropriate for the use of Research, Development, Test and Evaluation (R,D,T & E) funds as opposed to those appropriate for O&M (Operations and Maintenance) funds. What the U.S. Department of Defense calls “color of money.”

b. Amounts that were expended on contract that exceeded the authorized funding documents, which is largely based on the findings regarding the appropriate color of money. This would constitute a serious violation known as an Anti-Deficiency Act violation which, in layman’s terms, is directed to punish public employees for the misappropriation of government funds.

c. Expended amounts of O&M that exceeded the authorized levels.

d. Poor or non-existent program management and cost performance management.

e. Inappropriate contracting vehicles that, taken together, sidestepped more stringent oversight, aside from the award of a software solutions contract to the same company that defined the agency’s requirements.

Some of these are procedural and some are serious, particularly the Anti-deficiency Act (ADA) violations, are serious. In the Contracting Officer’s rulebook, you can withstand pedestrian procedural and administrative findings that are part and parcel of running an intensive contracting organization that acquires a multitude of supplies and services under deadline. But an ADA violation is the deadly one, since it is a violation of statute.

As a result of these findings, the recommendation is for DCMA to lose acquisition authority over the DoD micro-contracting level ($10,000). Organizationally and procedurally, this is a significant and mission-disruptive recommendation.

The Role and Importance of DCMA

DCMA performs an important role in contract compliance and oversight to ensure that public monies are spent properly and for the intended purpose. They perform this role mostly on contracts that are negotiated and entered into by other agencies and the military services within the Department of Defense, where they are assigned contract administration duties. Thus, the fact that DCMA’s internal IT acquisition systems and procedures were problematic is embarrassing.

But some perspective is necessary because there is a drive by some more extreme elements in Congress and elsewhere that would like to see the elimination of the agency. I believe that this would be a grave mistake. As John F. Kennedy is quoted as having said: “You don’t tear your fences down unless you know why they were put up.”

For those of you who were not around prior to the formation of DCMA or its predecessor organization, the Defense Contract Management Command (DCMC), it is important to note that the formation of the agency is a result of acquisition reform. Prior to 1989 the contract administration services (CAS) capabilities of the military services and various DoD offices varied greatly in capability, experience, and oversight effectiveness.Some of these duties had been assigned to what is now the Defense Logistics Agency (DLA), but major acquisition contracts remained with the Services.

For example, when I was on active duty as a young Navy Supply Corps Officer as part of the first class that was to be the Navy Acquisition Corps, I was taught cradle-to-grave contracting. That is, I learned to perform customer requirements development, economic analysis, contract planning, development of a negotiating position, contract negotiation, and contract administration–soup to nuts. The expense involved in developing and maintaining the skill set required of personnel to maintain such a broad-based expertise is unsustainable. For analogy, it is as if every member of a baseball club must be able to play all nine positions at the same level of expertise; it is impossible.

Furthermore, for contract administration a defense contractor would have contractual obligations for oversight in San Diego, where I was stationed, that were different from contracts awarded in Long Beach or Norfolk or any of the other locations where a contracting office was located. Furthermore, the military services, having their own organizational cultures, provided additional variations that created a plethora of unique requirements that added cost, duplication, inconsistency, and inter-organizational conflict.

This assertion is more than anecdotal. A series of studies were commissioned in the 1980s (the findings of which were subsequently affirmed) to eliminate duplication and inconsistency in the administration of contracts, particularly major acquisition programs. Thus, DCMC was first established under DLA and subsequently became its own agency. Having inherited many of the contracting field office, the agency has struggled to consolidate operations so that CAS is administered in a consistent manner across contracts. Because contract negotiation and program management still resides in the military services, there is a natural point of conflict between the services and the agency.

In my view, this conflict is a healthy one, as all power in the hands of a single individual, such as a program manager, would lead to more fraud, waste, and abuse, not less. Internal checks and balances are necessary in proper public administration, where some efficiency is sacrificed to accountability. It is not just the goal of government to “make the trains run on time”, but to perform oversight of the public’s money so that there is accountability in its expenditure, and integrity in systems and procedures. In the case of CAS, it is to ensure that what is being procured actually gets delivered in conformance to the contract terms and conditions designed to reduce the inherent risk in complex acquisition programs.

In order to do its job effectively, DCMA requires innovative digital systems to allow it to perform its CAS function. As a result, the agency must also possess an acquisition capability. Given the size of the task at hand in performing CAS on over $5 trillion of contract effort, the data involved is quite large, and the number of personnel geographically distributed. The inevitable comparisons to private industry will arise, but few companies in the world have to perform this level of oversight on such a large economic scale, which includes contracts comprising every major supplier to the U.S. Department of Defense, involving detailed knowledge of the management control systems of those companies that receive the taxpayer’s money. Thus, this is a uniquely difficult job. When one understands that in private industry the standard failure rate of IT projects is more than 70% percent, then one cannot help but be unimpressed by these findings, given the challenge.

Assessing the Findings and Recommendations

There is a reason why internal oversight documents of this sort stay confidential–it is because these are preliminary/draft findings and there are two sides to every story which may lead to revisions. In addition, reading these findings without the appropriate supporting documentation can lead one to the wrong impression and conclusions. But it is important to note that this was an internally generated investigation. The checks and balances of management oversight that should occur, did occur. But let’s take a close look at what the reports indicate so that we can draw some lessons. I also need to mention here that POGO’s conflation of the specific issues in this program as a “poster child” for cost overruns and schedule slippage displays a vast ignorance of DoD procurement systems on the part of the article’s author.

Money, Money, Money

The core issue in the findings revolves around the proper color of money, which seems to hinge on the definition of Commercial-Off-The-Shelf (COTS) software and the effort that was expended using the two main types of money that apply to the core contract: RDT&E and O&M.

Let’s take the last point first. It appears that the IWMS effort consisted of a combination of COTS and custom software. This would require acquisition, software familiarization, and development work. It appears that the CIO was essentially running a proof-of-concept to see what would work, and then incrementally transitioned to developing the solution.

What is interesting is that there is currently an initiative in the Department of Defense to do exactly what the DCMA CIO did as part of his own initiative in introducing a new technological approach to create IWMS. It is called Other Transactional Authority (OTA). The concept didn’t exist and was not authorized until the 2016 NDAA and is given specific statutory authority under 10 U.S.C. 2371b. This doesn’t excuse the actions that led to the findings, but it is interesting that the CIO, in taking an incremental approach to finding a solution, also did exactly what was recommended in the 2016 GAO report that POGO references in their article.

Furthermore, as a career Navy Supply Corps Officer, I have often gotten into esoteric discussions in contracts regarding the proper color of money. Despite the assertion of the investigation, there is a lot of room for interpretation in the DoD guidance, not to mention a stark contrast in interpreting the proper role of RDT&E and O&M in the procurement of business software solutions.

When I was on the NAVAIR staff and at OSD I ran into the difference in military service culture where what Air Force financial managers often specified for RDT&E would never be approved by Navy financial managers where, in the latter case, they specified that only O&M dollars applied, despite whether development took place. Given that there was an Air Force flavor to the internal investigation, I would be interested to know whether the opinion of the investigators in making an ADA determination would withstand objective scrutiny among a panel of government comptrollers.

I am certain that, given the differing mix of military and civil service cultures at DCMA–and the mixed colors of money that applied to the effort–that the legal review that was sought to resolve the issue. One of the principles of law is that when you rely upon legal advice to take an action that you have a defense, unless your state of mind and the corollary actions that you took indicates that you manipulated the system to obtain a result that shows that you intended to violate the law. I just do not see that here, based on what has been presented in the materials.

It is very well possible that an inadvertent ADA violation occurred by default because of an improper interpretation of the use of the monies involved. This does not rise to the level of a scandal. But going back to the confusion that I have faced from my own experiences on active duty, I certainly hope that this investigation is not used as a precedent to review all contracts under the approach of accepting a post-hoc alternative interpretation by another individual who just happens to be an inspector long after a reasonable legal determination was made, regardless of how erroneous the new expert finds the opinion. This is not an argument against accountability, but absent corruption or criminal intent, a legal finding is a valid defense and should stand as the final determination for that case.

In addition, this interpretation of RDT&E vs. O&M relies upon an interpretation of COTS. I daresay that even those who throw that term around and who are familiar with the FAR fully understand what constitutes COTS when the line between adaptability and point solutions is being blurred by new technology.

Where the criticism is very much warranted are those areas where the budget authority would have been exceeded in any event–and it is here that the ADA determination is most damning. It is one thing to disagree on the color of money that applies to different contract line items, but it is another to completely lack financial control.

Part of the reason for lack of financial control was the absence of good contracting practices and the imposition of program management.

Contracts 101

While I note that the CIO took an incremental approach to IWMS–what a prudent manager would seem to do–what was lacking was a cohesive vision and a well-informed culture of compliance to acquisition policy that would avoid even the appearance of impropriety and favoritism. Under the OTA authority that I reference above as a new aspect of acquisition reform, the successful implementation of a proof-of-concept does not guarantee the incumbent provider continued business–salient characteristics for the solution are publicized and the opportunity advertised under free and open competition.

After all, everyone has their favorite applications and, even inadvertently, an individual can act improperly because of selection bias. The procurement procedures are established to prevent abuse and favoritism. As a solution provider I have fumed quite often where a selection was made without competition based on market surveys or use of a non-mandatory GSA contract, which usually turn out to be a smokescreen for pre-selection.

There are two areas of fault on IMWS from the perspective of acquisition practice, and another in relation to program management.

These are the initial selection of Apprio, which had laid out the initial requirements and subsequently failed to have the required integration functionality, and then, the selection of Discover Technologies under a non-mandatory GSA Blanket Purchase Agreement (BPA) contract under a sole source action. Furthermore, the contract type was not appropriate to the task at hand, and the arbitrary selection of Discover precluded the agency finding a better solution more fit to its needs.

The use of the GSA BPA allowed managers, however, to essentially spit the requirements to stay below more stringent management guidelines–an obvious violation of acquisition regulation that will get you removed from your position. This leads us to what I think is the root cause of all of these clearly avoidable errors in judgment.

Program Management 101

Personnel in the agency familiar with the requirements to replace the aging procurement management system understood from the outset that the total cost would probably fall somewhere between $20M and $40M. Yet all effort was made to reduce the risk by splitting requirements and failing to apply a programmatic approach to a clearly complex undertaking.

This would have required the agency to take the steps to establish an acquisition strategy, open the requirement based on a clear performance work statement to free and open competition, and then to establish a program management office to manage the effort and to allow oversight of progress and assessment of risks in a formalized environment.

The establishment of a program management organization would have prevented the lack of financial control, and would have put in place sufficient oversight by senior management to ensure progress and achievement of organizational goals. In a word, a good deal of the decision-making was based on doing stupid things on purpose.

The Recommendations

In reviewing the recommendations of the internal investigation, I think my own personal involvement in a very similar issue from 1985 will establish a baseline for comparison.

As I indicated earlier, in the early 1980s, as a young Navy commissioned officer, I was part of the first class of what was to be the Navy Acquisition Corps, stationed at the Supply Center in San Diego, California. I had served as a contracting intern and, after extensive education through the University of Virginia Darden School of Business, the extended Federal Acquisition Regulation (FAR) courses that were given at the time at Fort Lee, Virginia, and coursework provided by other federal acquisition organizations and colleges, I attained my warrant as a contracting officer. I also worked on acquisition reform issues, some of which were eventually adopted by the Navy and DoD.

During this time NAS Miramar was the home of Top Gun. In 1984 Congressman Duncan Hunter (the elder not the currently indicted junior of the same name, though from the same San Diego district), inspired by news of $7,600 coffee maker and a $435 hammer publicized by the founders of POGO, was given documents by a disgruntled employee at the base regarding the acquisition of replacement E-2C ashtrays that had a cost of $300. He presented them to the Base Commander, which launched an investigation.

I served on the JAG investigation under the authority of the Wing Commander regarding the acquisitions and then, upon the firing of virtually the entire chain of command at NAS Miramar, which included the Wing Commander himself, became the Officer-in-Charge of Supply Center San Diego Detachment NAS Miramar. Under Navy Secretary Lehman’s direction I was charged with determining the root cause of the acquisition abuses and given 60-90 days to take immediate corrective action and clear all possible discrepancies.

I am not certain who initiated the firings of the chain of command. From talking with contemporaneous senior personnel at the time it appeared to have been instigated in a fit of pique by the sometimes volcanic Secretary of Defense Caspar Weinberger. While I am sure that Secretary Weinberger experienced some emotional release through that action, placed in perspective, his blanket firing of the chain of command, in my opinion, was poorly advised and counterproductive. It was also grossly unfair, given what my team and I found as the root cause.

First of all, the ashtray was misrepresented in the press as a $600 ashtray because during the JAG I had sent a sample ashtray to the Navy industrial activity at North Island with a request to tell me what the fabrication of one ashtray would cost and to provide the industrial production curve that would reduce the unit price to a reasonable level. The figure of $600 was to fabricate one. A “whistleblower” at North Island took this slice of information out of context and leaked it to the press. So the $300 ashtray, which was bad enough, became the $600 ashtray.

Second, the disgruntled employee who gave the files to Congressman Hunter had been laterally assigned out of her position as a contracting officer by the Supply Officer because of the very reason that the pricing of the ashtray was not reasonable, among other unsatisfactory performance measures that indicated that she was not fit to perform those duties.

Third, there was a systemic issue in the acquisition of odd parts. For some reason there was an ashtray in the cockpit of the E-2C. These aircraft were able to stay in the air an extended period of time. A pilot had actually decided to light up during a local mission and, his attention diverted, lost control of the aircraft and crashed. Secretary Lehman ordered corrective action. The corrective action taken by the squadron at NAS Miramar was to remove the ashtray from the cockpit and store them in a hangar locker.

Four, there was an issue of fraud. During inspection the spare ashtrays were removed and deposited in the scrap metal dumpster on base. The tech rep for the DoD supplier on base retrieved the ashtrays and sold them back to the government for the price to fabricate one, given that the supply system had not experienced enough demand to keep them in stock.

Fifth, back to the systemic issue. When an aircraft is to be readied for deployment there can be no holes representing missing items in the cockpit. A deploying aircraft with this condition is then grounded and a high priority “casuality report” or CASREP is generated. The CASREP was referred to purchasing which then paid $300 for each ashtray. The contracting officer, however, feeling under pressure by the high priority requisition, did not do due diligence in questioning the supplier on the cost of the ashtray. In addition, given that several aircraft deploy, there were a number of these requisitions that should have led the contracting officer to look into the matter more closely to determine price reasonableness.

Furthermore, I found that buying personnel were not properly trained, that systems and procedures were not established or enforced, that the knowledge of the FAR was spotty, and that procurements did not go through multiple stages of review to ensure compliance with acquisition law, proper documentation, and administrative procedure.

Note that in the end this “scandal” was born by a combination of systemic issues, poor decision-making, lack of training, employee discontent, and incompetence.

I successfully corrected the issues at NAS Miramar during the prescribed time set by the Secretary of the Navy, worked with the media to instill public confidence in the system, built up morale, established better customer service, reduced procurement acquisition lead times (PALT), recommended necessary disciplinary action where it seemed appropriate, particularly in relation to the problematic employee, recovered monies from the supplier, referred the fraud issues to Navy legal, and turned over duties to a new chain of command.

NAS Miramar procurement continued to do its necessary job and is still there.

What the higher chain of command did not do was to take away the procurement authority of NAS Miramar. It did not eliminate or reduce the organization. It did not close NAS Miramar.

It requires leadership and focus to take effective corrective action to not only fix a broken system, but to make it better while the corrective actions are being taken. As I outlined above, DCMA performs an essential mission. As it transitions to a data-driven approach and works to reduce redundancy and inefficiency in its systems, it will require more powerful technologies to support its CAS function, and the ability to acquire those technologies to support that function.

(Data) Transformation–Fear and Loathing over ETL in Project Management

ETL stands for data extract, transform, and load. This essential step is the basis for all of the new capabilities that we wish to acquire during the next wave of information technology: business analytics, big(ger) data, interdisciplinary insight into processes that provide insights into improving productivity and efficiency.

I’ve been dealing with a good deal of fear and loading regarding the introduction of this concept, even though in my day job my organization is a leading practitioner in the field in its vertical. Some of this is due to disinformation by competitors in playing upon the fears of the non-technically minded–the expected reaction of those who can’t do in the last throws of avoiding irrelevance. Better to baffle them with bullshit than with brilliance, I guess.

But, more importantly, part of this is due to the state of ETL and how it is communicated to the project management and business community at large. There is a great deal to be gained here by muddying the waters even by those who know better and have the technology. So let’s begin by clearing things up and making this entire field a bit more coherent.

Let’s start with the basics. Any organization that contains the interaction of people is a system. For purposes of a project management team, a business enterprise, or a governmental body we deal with a special class of systems known as Complex Adaptive Systems: CAS for short. A CAS is a non-linear learning system that reacts and evolves to its environment. It is complex because of the inter-relationships and interactions of more than two agents in any particular portion of the system.

I was first introduced to the concept of CAS through readings published out of the Santa Fe Institute in New Mexico. Most noteworthy is the work The Quark and the Jaguar by the physicist Murray Gell-Mann. Gell-Mann is received the Nobel in physics in 1969 for his work on elementary particles, such as the quark, and is co-founder of the Institute. He also was part of the team that first developed simulated Monte Carlo analysis during a period he spent at RAND Corporation. Anyone interested in the basic science of quanta and how the universe works that then leads to insights into subjects such as day-to-day probability and risk should read this book. It is a good popular scientific publication written by a brilliant mind, but very relevant to the subjects we deal with in project management and information science.

Understanding that our organizations are CAS allows us to apply all sorts of tools to better understand them and their relationship to the world at large. From a more practical perspective, what are the risks involved in the enterprise in which we are engaged and what are the probabilities associated with any of the range of outcomes that we can label as success. For my purposes, the science of information theory is at the forefront of these tools. In this world an engineer by the name of Claude Shannon working at Bell Labs essentially invented the mathematical basis for everything that followed in the world of telecommunications, generating, interpreting, receiving, and understanding intelligence in communication, and the methods of processing information. Needless to say, computing is the main recipient of this theory.

Thus, all CAS process and react to information. The challenge for any entity that needs to survive and adapt in a continually changing universe is to ensure that the information that is being received is of high and relevant quality so that the appropriate adaptation can occur. There will be noise in the signals that we receive. What we are looking for from a practical perspective in information science are the regularities in the data so that we can make the transformation of receiving the message in a mathematical manner (where the message transmitted is received) into the definition of information quality that we find in the humanities. I believe that we will find that mathematical link eventually, but there is still a void there. A good discussion of this difference can be found here in the on-line publication Double Dialogues.

Regardless of this gap, the challenge of those of us who engage in the business of ETL must bring to the table the ability not only to ensure that the regularities in the information are identified and transmitted to the intended (or necessary) users, but also to distinguish the quality of the message in the terms of the purpose of the organization. Shannon’s equation is where we start, not where we end. Given this background, there are really two basic types of data that we begin with when we look at a set of data: structured and unstructured data.

Structured data are those where the qualitative information content is either predefined by its nature or by a tag of some sort. For example, schedule planning and performance data, regardless of the idiosyncratic/proprietary syntax used by a software publisher, describes the same phenomena regardless of the software application. There are only so many ways to identify snow–and, no, the Inuit people do not have 100 words to describe it. Qualifiers apply in the humanities, but usually our business processes more closely align with statistical and arithmetic measures. As a result, structured data is oftentimes defined by its position in a hierarchical, time-phased, or interrelated system that contains a series of markers, indexes, and tables that allow it to be interpreted easily through the identification of a Rosetta stone, even when the system, at first blush, appears to be opaque. When you go to a book, its title describes what it is. If its content has a table of contents and/or an index it is easy to find the information needed to perform the task at hand.

Unstructured data consists of the content of things like letters, e-mails, presentations, and other forms of data disconnected from its source systems and collected together in a flat repository. In this case the data must be mined to recreate what is not there: the title that describes the type of data, a table of contents, and an index.

All data requires initial scrubbing and pre-processing. The difference here is the means used to perform this operation. Let’s take the easy path first.

For project management–and most business systems–we most often encounter structured data. What this means is that by understanding and interpreting standard industry terminology, schemas, and APIs that the simple process of aligning data to be transformed and stored in a database for consumption can be reduced to a systemic and repeatable process without the redundancy of rediscovery applied in every instance. Our business intelligence and business analytics systems can be further developed to anticipate a probable question from a user so that the query is pre-structured to allow for near immediate response. Further, structuring the user interface in such as way as to make the response to the query meaningful, especially integrated with and juxtaposed other types of data requires subject matter expertise to be incorporated into the solution.

Structured ETL is the place that I most often inhabit as a provider of software solutions. These processes are both economical and relatively fast, particularly in those cases where they are applied to an otherwise inefficient system of best-of-breed applications that require data transfers and cross-validation prior to official reporting. Time, money, and effort are all saved by automating this process, improving not only processing time but also data accuracy and transparency.

In the case of unstructured data, however, the process can be a bit more complicated and there are many ways to skin this cat. The key here is that oftentimes what seems to be unstructured data is only so because of the lack of domain knowledge by the software publisher in its target vertical.

For example, I recently read a white paper published by a large BI/BA publisher regarding their approach to financial and accounting systems. My own experience as a business manager and Navy Supply Corps Officer provide me with the understanding that these systems are highly structured and regulated. Yet, business intelligence publishers treated this data–and blatantly advertised and apparently sold as state of the art–an unstructured approach to mining this data.

This approach, which was first developed back in the 1980s when we first encountered the challenge of data that exceeded our expertise at the time, requires a team of data scientists and coders to go through the labor- and time-consuming process of pre-processing and building specialized processes. The most basic form of this approach involves techniques such as frequency analysis, summarization, correlation, and data scrubbing. This last portion also involves labor-intensive techniques at the microeconomic level such as binning and other forms of manipulation.

This is where the fear and loathing comes into play. It is not as if all information systems do not perform these functions in some manner, it is that in structured data all of this work has been done and, oftentimes, is handled by the database system. But even here there is a better way.

My colleague, Dave Gordon, who has his own blog, will emphasize that the identification of probable questions and configuration of queries in advance combined with the application of standard APIs will garner good results in most cases. Yet, one must be prepared to receive a certain amount of irrelevant information. For example, the query on Google of “Fun Things To Do” that you may use if you are planning for a weekend will yield all sorts of results, such as “50 Fun Things to Do in an Elevator.”  This result includes making farting sounds. The link provides some others, some of which are pretty funny. In writing this blog post, a simple search on Google for “Google query fails” yields what can only be described as a large number of query fails. Furthermore, this approach relies on the data originator to have marked the data with pointers and tags.

Given these different approaches to unstructured data and the complexity involved, there is a decision process to apply:

1. Determine if the data is truly unstructured. If the data is derived from a structured database from an existing application or set of applications, then it is structured and will require domain expertise to inherit the values and information content without expending unnecessary resources and time. A structured, systemic, and repeatable process can then be applied. Oftentimes an industry schema or standard can be leveraged to ensure consistency and fidelity.

2. Determine whether only a portion of the unstructured data is relative to your business processes and use it to append and enrich the existing structured data that has been used to integrate and expand your capabilities. In most cases the identification of a Rosetta Stone and standard APIs can be used to achieve this result.

3. For the remainder, determine the value of mining the targeted category of unstructured data and perform a business case analysis.

Given the rapidly expanding size of data that we can access using the advancing power of new technology, we must be able to distinguish between doing what is necessary from doing what is impressive. The definition of Big Data has evolved over time because our hardware, storage, and database systems allow us to access increasingly larger datasets that ten years ago would have been unimaginable. What this means is that–initially–as we work through this process of discovery, we will be bombarded with a plethora of irrelevant statistical measures and so-called predictive analytics that will eventually prove out to not pass the “so-what” test. This process places the users in a state of information overload, and we often see this condition today. It also means that what took an army of data scientists and developers to do ten years ago takes a technologist with a laptop and some domain knowledge to perform today. This last can be taught.

The next necessary step, aside from applying the decision process above, is to force our information systems to advance their processing to provide more relevant intelligence that is visualized and configured to the domain expertise required. In this way we will eventually discover the paradox that effectively accessing larger sets of data will yield fewer, more relevant intelligence that can be translated into action.

At the end of the day the manager and user must understand the data. There is no magic in data transformation or data processing. Even with AI and machine learning it is still incumbent upon the people within the organization to be able to apply expertise, perspective, knowledge, and wisdom in the use of information and intelligence.

Friday Hot Washup: Daddy Stovepipe sings the Blues, and Net Neutrality brought to you by Burger King

Daddy Stovepipe sings the Blues — Line and Staff Organizations (and how they undermine organizational effectiveness)

In my daily readings across the web I came upon this very well written blog post by Glen Alleman at his Herding Cat’s blog. The eternal debate in project management surrounds when done is actually done–and what is the best measurement of progress toward the completion of the end item application?

Glen rightly points to the specialization among SMEs in the PM discipline, and the differences between their methods of assessment. These centers of expertise are still aligned along traditional line and staff organizations that separate scheduling, earned value, system engineering, financial management, product engineering, and other specializations.

I’ve written about this issue where information also follows these stove-piped pathways–multiple data streams with overlapping information, but which resists effective optimization and synergy because of the barriers between them. These barriers may be social or perceptual, which then impose themselves upon the information systems that are constructed to support them.

The manner in which we face and interpret the world is the core basis of epistemology. When we develop information systems and analytical methodologies, whether we are consciously aware of it or not, we delve into the difference between justified belief and knowledge. I see the confusion of these positions in daily life and in almost all professions and disciplines. In fact, most of us find ourselves jumping from belief to knowledge effortlessly without being aware of this internal contradiction–and the corresponding reduction in our ability to accurately perceive reality.

The ability to overcome our self-imposed constraints is the key but, I think, our PM organizational structures must be adjusted to allow for the establishment of a learning environment in relation to data. The first step in this evolution must be the mentoring and education of a discipline that combines these domains. What this proposes is that no one individual need know everything about EVM, scheduling, systems engineering, and financial management. But the business environment today is such, if the business or organization wishes to be prepared for the world ahead, to train transition personnel toward a multi-disciplinary project management competency.

I would posit, contrary to Glen’s recommendation, that no one discipline claim to be the basis for cross-functional integration, only because it may be a self-defeating one. In the book Networks, Crowds, and Markets: Reasoning about a Highly Connected World by David Easley and Jon Kleinberg of Cornell, our social systems are composed of complex networks, but where negative perceptions develop when the network is no longer considered in balance. This subtle and complex interplay of perceptions drive our ability to work together.

It also affects whether we will stay safe the comfort zone of having our information systems tell us what we need to analyze, or whether we apply a more expansive view of leveraging new information systems that are able to integrate ever expanding sets of relevant data to give us a more complete picture of what constitutes “done.”

Hold the Pickle, Hold the Lettuce, Special Orders Don’t Upset Us: Burger King explains Net Neutrality

The original purpose of the internet has been the free exchange of ideas and knowledge. Initially, under ARPANET, Lawrence Roberts and later Bob Kahn, the focus was on linking academic and research institutions so that knowledge could be shared resulting in collaboration that would overcome geographical barriers. Later the Department of Defense, NASA, and other government organizations highly dependent on R&D were brought into the new internet community.

To some extent there still are pathways within what is now broadly called the Web, to find and share such relevant information with these organizations. With the introduction of commercialization in the early 1990s, however, it has been increasingly hard to perform serious research.

For with the expansion of the internet to the larger world, the larger world’s dysfunctions and destructive influences also entered. Thus, the internet has transitioned from a robust First Amendment free speech machine to a place that also harbors state-sponsored psy-ops and propaganda. It has gone form a safe space for academic freedom and research to a place of organized sabotage, intrusion, theft, and espionage. It has transitioned from a highly organized professional community that hewed to ethical and civil discourse, to one that harbors trolls, prejudice, hostility, bullying, and other forms of human dysfunction. Finally and most significantly, it has become dominated by commercial activity, dominated by high tech giants that stifle innovation, and social networking sites that also allow, applying an extreme Laissez-faire attitude, magnify and spread the more dysfunctional activities found in the web as a whole.

At least for those who still looked to the very positive effects of the internet there was net neutrality. The realization that blogs like this one and the many others that I read on a regular basis, including mainstream news, and scientific journals still were available without being “dollarized” in the words of the naturalist John Muir.

Unfortunately this is no longer the case, or will no longer be the case, perhaps, when the legal dust settles. Burger King has placed it marker down and it is a relevant and funny one. Please enjoy and have a great weekend.

 

Post-Workshop Talking Blues — No Bucks, No Buck Rogers: Cashflow Analysis in Projects (Somewhat Wonkish)

When I used this analogy the week before last during the last Integrated Project Management Workshop in the D.C. area I was accused of dating myself–and perhaps it is true. For those wondering the quote was popularized by the 1983 movie The Right Stuff, which was based on the 1979 book written by Tom Wolfe of the same title. The book and movie was about the beginnings of the U.S. space program culminating in the creation of NASA and the Project Mercury program.

A clip from the movie follows:

It goes without saying that while I was familiar as a boy with Project Mercury and followed the seven astronauts as did the rest of the country, transfixed on the prospect of space exploration during the days of the New Frontier, Buck Rogers was from the childhood of my father’s generation through, at first, its radio program, and then through the serials that were released to the movie theaters during the 1930s.

The point of the quote, of course, is that Project Mercury’s success was based on its ability to obtain funding and, no doubt, the Mercury 7 astronauts so inspired the imagination of the nation that even the most parsimonious Member of Congress could not help but provide it with sufficient funding for success. That this was also the era of the “space race” with the Soviet Union, which also helped to spur funding.

The lesson of “No Bucks, No Buck Rogers” also applies to project management, but not just in the use of imagery and marketing to gain funding. Instead, the principle applies through a more mundane part of the discipline: financial management and the relationship between cash flow and project performance.

What I am referring to as cash flow is not the burn rate of expenditures against an end point, but the intersection of sufficient money at the right time programmed in accordance with the project plan (in alignment with both the IMS and PMB), and informed by project performance.

To those unfamiliar with this method it sounds similar to earned value management, but it is not. EVM informs our decision, but the analysis is not the same.

First, in using this analysis the cumulative actual cost of work performed (ACWP in earned value) should be compared to accrued expenditures for the project. These figures will not be exact, but will provide an indication whether accruals to date have been in line with what was forecasted. In government contracting and project management, these figures will also be somewhat off because earned value figures do not include fee or profit, while financial management figures will include fee or profit. Understanding the profit center from which the financial expenditures are being accrued will allow for a reconciliation of these differences.

Secondly, if projected accruals against the project plan begin to deviate, it is an early indication of programmatic risk being manifested in the physical expenditures of the project. For example, if management anticipates that there will be a delay in project execution in some area, they may decide to defer acquisition of spare parts used in the construction of a component, or they may delay the award of a subcontract that was meant to augment staff in an area requiring specialized expertise.

Third, and conversely, deviations of expenditures for needed materials or manpower may adversely affect project execution, and provide an early warning that such shortages or misalignments will move project accomplishment to the right. For example, a company may have underestimated the combined Procurement Action Lead Time (PALT) and delivery of critical materials, which will now arrive much later than anticipated. This misalignment will cascade through the schedule and future planned work.

For both of these previous conditions, the proper determination of cause-and-effect is essential, since either may appear to suggest the opposite cause.

Fourth, variances in performance either in earned value achievement or schedule performance may require an adjustment to the type of money being provided. For example, when a project fails to execute and risk is manifested in terms of cost and/or schedule, financial management and budgeting personnel, always under pressure to apply excess funds to more immediate needs, may mistakenly believe that a budget mark (a decrease) is appropriate since the allocated money will not be executed in the current time-frame.

But this is not necessarily the case. Performance management data tracks the performance measurement baseline (PMB) for the life of the project, but funding has a finite period in which it can be executed. In government contracting it is not uncommon for there to be different “colors” of money: Research, Development, Test & Evaluation (RDT&E), Procurement, Operations and Maintenance (O&M), and others. Furthermore, these types of appropriations have different expiration dates: two years in terms of RDT&E, three years for procurement, and one year for O&M. The financial management plan takes into account the life of money allocated to the project, as well as the costs of activities necessary to project execution. The time frame for financial execution is shorter and, therefore, more sensitive to risks or variances than project plans that are projected across a longer period of time.

For an R&D program experiencing risk during a particular portion of its PMB, for example, a variance this year may require not only a steady funding profile, but a larger expenditure to handle risk. Marking two-year RDT&E money in its first year in this case would be a mistake, of course, but *not* properly anticipating the proper level of risk adjusted expenditures to handle risk may exacerbate the ability of the project to recover and execute, causing it to fall into a spiral of compounding misalignments and variances from which it may never recover.

Thus, what we can see is that, oftentimes, the availability of cash–and the right kind of cash at the right time–will have as much impact on project execution as the factors of technical and engineering risk. Furthermore, tracking and reconciling the financial plan against actual accomplishment will provide a very detailed early indicator into project performance since it is sensitive to deviations in the fiscal plan.

Postscript.

For those not savvy about the cultural reference to Buck Rogers what follows is a sampling of the first of what became a movie serial in the 1930s, which originated as a radio “space opera”. Later it became a TV series in 1950 as well. For the record, I was not around yet when these were popular, though I did watch the reruns on Saturday mornings in the 1960s and early 1970s.

 

 

 

 

 

 

 

 

 

 

Money for Nothing — Project Performance Data and Efficiencies in Timeliness

I operate in a well regulated industry focused on project management. What this means practically is that there are data streams that flow from the R&D activities, recording planning and progress, via control and analytical systems to both management and customer. The contract type in most cases is Cost Plus, with cost and schedule risk often flowing to the customer in the form of cost overruns and schedule slippages.

Among the methodologies used to determine progress and project eventual outcomes is earned value management (EVM). Of course, this is not the only type of data that flows in performance management streams, but oftentimes EVM is used as shorthand to describe all of the data captured and submitted to customers in performance management. Other planning and performance management data includes time-phased scheduling of tasks and activities, cost and schedule risk assessments, and technical performance.

Previously in my critique regarding the differences between project monitoring and project management (before Hurricane Irma created some minor rearranging of my priorities), I pointed out that “looking in the rear view mirror” was often used as an excuse for by-passing unwelcome business intelligence. I followed this up with an intro to the synergistic economics of properly integrated data. In the first case I answered the critique demonstrating that it is based on an old concept that no longer applies. In the second case I surveyed the economics of data that drives efficiencies. In both cases, new technology is key to understanding the art of the possible.

As I have visited sites in both government and private industry, I find that old ways of doing things still persist. The reason for this is multivariate. First, technology is developing so quickly that there is fear that one’s job will be eliminated with the introduction of technology. Second, the methodology of change agents in introducing new technology often lacks proper socialization across the various centers of power that inevitably exist in any organization. Third, the proper foundation to clearly articulate the need for change is not made. This last is particularly important when stakeholders perform a non-rational assessment in their minds of cost-benefit. They see many downsides and cannot accept the benefits, even when they are obvious. For more on this and insight into other socioeconomic phenomena I strongly recommend Daniel Kahneman’s Thinking Fast and Slow. There are other reasons as well, but these are the ones that are most obvious when I speak with individuals in the field.

The Past is Prologue

For now I will restrict myself to the one benefit of new technology that addresses the “looking in the rear window” critique. It is important to do so because the critique is correct in application (for purposes that I will outline) if incorrect in its cause-and-effect. It is also important to focus on it because the critique is so ubiquitous.

As I indicated above, there are many sources of data in project management. They derive from the following systems (in brief):

a. The planning and scheduling applications, which measure performance through time in the form of discrete activities and events. In the most sophisticated implementations, these applications will include the assignment of resources, which requires the integration of these systems with resource management. Sometimes simple costs are also assigned and tracked through time as well.

b. The cost performance (earned value) applications, which ideally are aligned with the planning and scheduling applications, providing cross-integration with WBS and OBS structures, but focused on work accomplishment defined by the value of work completed against a baseline plan. These performance figures are tied to work accomplishment through expended effort collected by and, ideally, integrated with the financial management system. It involves the proper application of labor rates and resource expenditures in the accomplishment of the work to not only provide an statistical assessment of performance to date, but a projection of likely cost performance outcomes at completion of the effort.

c. Risk assessment applications which, depending of their sophistication and ease of use, provide analysis of possible cost and schedule outcomes, identify the sensitivity of particular activities and tasks, provide an assessment of alternative driving and critical paths, and apply different models of baseline performance to predict future outcomes.

d. Systems engineering applications that provide an assessment of technical performance to date and the likely achievement of technical parameters within the scope of the effort.

e. The financial management applications that provide an accounting of funds allocation, cash-flow, and expenditure, including planning information regarding expenditures under contract and planned expenditures in the future.

These are the core systems of record upon which performance information is derived. There are others as well, depending on the maturity of the project such as ERP systems and MRP systems. But for purposes of this post, we will bound the discussion to these standard sources of data.

In the near past, our ability to understand the significance of the data derived from these systems required manual processing. I am not referring to the sophistication of human computers of 1960s and before, dramatized to great effect in the uplifting movie Hidden Figures. Since we are dealing with business systems, these methodologies were based on simple business metrics and other statistical methods, including those that extended the concept of earned value management.

With the introduction of PCs in the workplace in the 1980s, desktop spreadsheet applications allowed this data to be entered, usually from printed reports. Each analyst not only used standard methods common in the discipline, but also developed their own methods to process and derive importance from the data, transforming it into information and useful intelligence.

Shortly after this development simple analytical applications were introduced to the market that allowed for pairing back the amount of data deriving from some of these systems and performing basic standard calculations, rendering redundant calculations unnecessary. Thus, for example, instead of a person having to calculate multiple estimates to complete, the application could perform those calculations as part of its functionality and deliver them to the analyst for use in, hopefully, their own more extensive assessments.

But even in this case, the data flow was limited to the EVM silo. The data streams relating to schedule, risk, SE, and FM were left to their own devices, oftentimes requiring manual methods or, in the best of cases, cut-and-paste, to incorporate data from reports derived from these systems. In the most extreme cases, for project oversight organizations, this caused analysts to acquire a multiplicity of individual applications (with the concomitant overhead and complexity of understanding differing lexicons and software application idiosyncrasies) in order to read proprietary data types from the various sources just to perform simple assessments of the data before even considering integrating it properly into the context of all of the other project performance data that was being collected.

The bottom line of outlining these processes is to note that, given a combination of manual and basic automated tools, that putting together and reporting on this data takes time, and time, as Mr. Benjamin Franklin noted, is money.

By itself the critique that “looking in the rear view mirror” has no value and attributing it to one particular type of information (EVM) is specious. After all, one must know where one has been and presently is before you can figure out where you need to go and how to get there and EVM is just one dimension of a multidimensional space.

But there is a utility value associated with the timing and locality of intelligence and that is the issue.

Contributors to time

Time when expended to produce something is a form of entropy. For purposes of this discussion at this level of existence, I am defining entropy as availability of the energy in a system to do work. The work in this case is the processing and transformation of data into information, and the further transformation of information into usable intelligence.

There are different levels and sub-levels when evaluating the data stream related to project management. These are:

a. Within the supplier/developer/manufacturer

(1) First tier personnel such as Control Account Managers, Schedulers (if separate), Systems Engineers, Financial Managers, and Procurement personnel among other actually recording and verifying the work accomplishment;

(2) Second tier personnel that includes various levels of management, either across teams or in typical line-and-staff organizations.

b. Within customer and oversight organizations

(1) Reporting and oversight personnel tasks with evaluating the fidelity of specific business systems;

(2) Counterpart project or program officer personnel tasked with evaluating progress, risk, and any factors related to scope execution;

(3) Staff organizations designed to supplement and organize the individual project teams, providing a portfolio perspective to project management issues that may be affected by other factors outside of the individual project ecosystem;

(4) Senior management at various levels of the organization.

Given the multiplicity of data streams it appears that the issue of economies is vast until it is understood that the data that underlies the consumers of the information is highly structured and specific to each of the domains and sub-domains. Thus there are several opportunities for economies.

For example, cost performance and scheduling data have a direct correlation and are closely tied. Thus, these separate streams in the A&D industry were combined under a common schema, first using the UN/CEFACT XML, and now transitioning to a more streamlined JSON schema. Financial management has gone through a similar transition. Risk and SE data are partially incorporated into project performance schemas, but the data is also highly structured and possesses commonalities to be directly accessed using technologies that effectively leverage APIs.

Back to the Future

The current state, despite advances in the data formats that allow for easy rationalization and normalization of data that breaks through propriety barriers, still largely is based a slightly modified model of using a combination of manual processing augmented by domain-specific analytical tools. (Actually sub-domain analytical tools that support sub-optimization of data that are a barrier to incorporation of cross-domain integration necessary to create credible project intelligence).

Thus, it is not unusual at the customer level to see project teams still accepting a combination of proprietary files, hard copy reports, and standard schema reports. Usually the data in these sources is manually entered into Excel spreadsheets or a combination of Excel and some domain-specific analytical tool (and oftentimes several sub-specialty analytical tools). After processing, the data is oftentimes exported or built in PowerPoint in the form of graphs or standard reporting formats. This is information management by Excel and PowerPoint.

In sum, in all too many cases the project management domain, in terms of data and business intelligence, continues to party like it is 1995. This condition also fosters and reinforces insular organizational domains, as if the project team is disconnected from and can possess goals antithetical and/or in opposition to the efficient operation of the larger organization.

A typical timeline goes like this:

a. Supplier provides project performance data 15-30 days after the close of a period. (Some contract clauses give more time). Let’s say the period closed at the end of July. We are now effectively in late August or early September.

b. Analysts incorporate stove-piped domain data into their Excel spreadsheets and other systems another week or so after submittal.

c. Analysts complete processing and analyzing data and submit in standard reporting formats (Excel and PowerPoint) for program review four to six weeks after incorporation of the data.

Items a through c now put a typical project office at project review for July information at the end of September or beginning of October. Furthermore, this information is focused on individual domains, and given the lack of cross-domain knowledge, can be contradictory.

This system is broken.

Even suppliers who have direct access to systems of record all too often rely on domain-specific solutions to be able to derive significance from the processing of project management data. The larger suppliers seem to have recognized this problem and have been moving to address it, requiring greater integration across solutions. But the existence of a 15-30 day reconciliation period after the end of a period, and formalized in contract clauses, is indicative of an opportunity for greater efficiency in that process as well.

The Way Forward

But there is another way.

The opportunities for economy in the form of improvements in time and effort are in the following areas, given the application of the right technology:

  1. In the submission of data, especially by finding data commonalities and combining previously separate domain data streams to satisfy multiple customers;
  2. In retrieving all data so that it is easily accessible to the organization at the level of detailed required by the task at hand;
  3. In processing this data so that it can converted by the analyst into usable intelligence;
  4. In properly accessing, displaying, and reporting properly integrated data across domains, as appropriate, to each level of the organization regardless of originating data stream.

Furthermore, there opportunities to realizing business value by improving these processes:

  1. By extending expertise beyond a limited number of people who tend to monopolize innovations;
  2. By improving organizational knowledge by incorporating innovation into the common system;
  3. By gaining greater insight into more reliable predictors of project performance across domains instead of the “traditional” domain-specific indices that have marginal utility;
  4. By developing a project focused organization that breaks down domain-centric thinking;
  5. By developing a culture that ties cross-domain project knowledge to larger picture metrics that will determine the health of the overarching organization.

It is interesting that when I visit the field how often it is asserted that “the technology doesn’t matter, it’s process that matters”.

Wrong. Technology defines the art of the possible. There is no doubt that in an ideal world we would optimize our systems prior to the introduction of new technology. But that assumes that the most effective organization (MEO) is achievable without technological improvements to drive the change. If one cannot efficiently integrate all submitted cross-domain information effectively and efficiently using Excel in any scenario (after all, it’s a lot of data), then the key is the introduction of new technology that can do that very thing.

So what technologies will achieve efficiency in the use of this data? Let’s go through the usual suspects:

a. Will more effective use of PowerPoint reduce these timelines? No.

b. Will a more robust set of Excel workbooks reduce these timelines? No.

c. Will an updated form of a domain-specific analytical tool reduce these timelines? No.

d. Will a NoSQL solution reduce these timelines? Yes, given that we can afford the customization.

e. Will a COTS BI application that accepts a combination of common schemas and APIs reduce these timelines? Yes.

The technological solution must be fitted to its purpose and time. Technology matters because we cannot avoid the expenditure of time or energy (entropy) in the processing of information. We can perform these operations using a large amount of energy in the form of time and effort, or we can conserve time and effort by substituting the power of computing and information processing. While we will never get to the point where we completely eliminate entropy, our application of appropriate technology makes it seem as if effort in the form of time is significantly reduced. It’s not quite money for nothing, but it’s as close as we can come and is an obvious area of improvement that can be made for a relatively small investment.

Synergy — The Economics of Integrated Project Management

The hot topic lately in meetings and the odd conference on Integrated Project Management (IPM) often focuses on the mechanics of achieving that state, bound by the implied definition of current regulation, which has also become–not surprisingly–practice. I think this is a laudable goal, particularly given both the casual resistance to change (which always there by definition to some extent) and in the most extreme cases a kind of apathy.

I addressed the latter condition in my last post by an appeal to professionalism, particularly on the part of those in public administration. But there is a more elemental issue here than the concerns of project analysts, systems engineers, and the associated information managers. While this level of expertise is essential in the development of innovation, relying too heavily on this level in the organization creates an internal organizational conflict that creates the risk that the innovation is transient and rests on a slender thread. Association with any one manager also leaves innovation vulnerable due to the “not invented here” tact taken by many new managers in viewing the initiatives of a predecessor. In business this (usually self-defeating) approach becomes more extreme the higher one goes in the chain of command (the recent Sears business model anyone?).

The key, of course, is to engage senior managers and project/program managers in participating in the development of this important part of business intelligence. A few suggestions on how to do this follow, but the bottom line is this: money and economics makes the implementation of IPM an essential component of business intelligence.

Data, Information, and Intelligence – Analysis vs. Reporting

Many years ago using manual techniques, I was employed in activities that required that I seek and document data from disparate sources, seemingly unconnected, and find the appropriate connections. The initial connection was made with a key. It could be a key word, topic, individual, technology, or government. The key, however, wasn’t the end of the process. The validity of the relationship needed to be verified as more than mere coincidence. This is a process well known in the community specializing in such processes, and two good sources to understand how this was done can be found here and here.

It is a well trod path to distinguish between the elements that eventually make up intelligence so I will not abuse the reader in going over it. Needless to say that a bit of data is the smallest element of the process, with information following. For project management what is often (mis)tagged as predictive analytics and analysis is really merely information. Thus, when project managers and decision makers look at the various charts and graphs employed by their analysts they are usually greeted with a collective yawn. Raw projections of cost variance, cost to complete, schedule variance, schedule slippage, baseline execution, Monte Carlo risk, etc. are all building blocks to employing business intelligence. But in and of themselves they are not intelligence because these indicators require analysis, weighting, logic testing, and, in the end, an assessment that is directly tied to the purpose of the organization.

The role and application of digitization is to make what was labor intensive less so. In most cases this allows us to apply digital technology to its strength–calculation and processing of large amounts of data to create information. Furthermore, digitization now allows for effective lateral integration among datasets given a common key, even if there are multiple keys that act in a chain from dataset to dataset.

At the end of the line what we are left with is a strong correlation of data integrated across a number of domains that contribute to a picture of how an effort is performing. Still, even given the most powerful heuristics, a person–the consumer–must validate the data to determine if the results possess validity and fidelity. For project management this process is not as challenging as, say, someone using raw social networking data. Project management data, since it is derived from underlying systems that through their processing mimic highly structured processes and procedures, tends to be “small”, even when it can be considered Big Data form the shear perspective of size. It is small Big Data.

Once data has been accumulated, however, it must be assessed so as to ensure that the parts cohere. This is done by assessing the significance and materiality of those parts. Once this is accomplished the overall assessment must then be constructed so that it follows logically from the data. That is what constitutes “actionable intelligence”: analysis of present condition, projected probable outcomes, recommended actions with alternatives. The elements of this analysis–charts, graphs, etc., are essential in reporting, but reporting these indices is not the purpose of the process. The added value of an analyst lies in the expertise one possesses. Without this dimension a machine could do the work. The takeaway from this point, however, isn’t to substitute the work with software. It is to develop analytical expertise.

What is Integrated Project Management?

In my last post I summed up what IPM is, but some elaboration and refinement is necessary.

I propose that Integrated Project Management is defined as that information necessary to derive actionable intelligence from all of the relevant cross-domain information involved in the project organization. This includes cost performance, schedule performance, financial performance and execution, contract implementation, milestone achievement, resource management, and technical performance. Actionable intelligence in this context, as indicated above, is that information that is relevant to the project decision-making authority which effectively identifies specific probable qualitative and quantitative risks, risk impact, and risk handling necessary to make project trade-offs, project re-baselining or re-scope, cost-as-an-independent variable (CAIV), or project cancellation decisions. Underlying all of this are feedback loop systems assessments to ensure that there is integrity and fidelity in our business systems–both human and digital.

The data upon which IPM is derived comes from a finite number of sources. Thus, project management data lends itself to solutions that break down proprietary syntax and terminology. This is really the key to achieving IPM and one that has garnered some discussion when discussing the process of data normalization and rationalization with other IT professionals. The path can be a long one: using APIs to perform data-mining directly against existing tables or against a data repository (or warehouse or lake), or pre-normalizing the data in a schema (given both the finite nature of the data and the finite–and structured–elements of the processes being documented in data).

Achieving normalization and rationalization in this case is not a notional discussion–in my vocation I provide solutions that achieve this goal. In order to do so one must expand their notion of the architecture of the appropriate software solution. The mindset of “tools” is at the core of what tends to hold back progress in integration, that is, the concept of a “tool” is one that is really based on an archaic approach to computing. It assumes that a particular piece of software must limit itself to performing limited operations focused on a particular domain. In business this is known as sub-optimization.

Oftentimes this view is supported by the organization itself where the project management team is widely dispersed and domains hoard information. The rice bowl mentality has long been a bane of organizational effectiveness. Organizations have long attempted to break through these barriers using various techniques: cross-domain teams, integrated product teams, and others.

No doubt some operations of a business must be firewalled in such a way. The financial management of the enterprise comes to mind. But when it comes to business operations, the tools and rice bowl mindset is a self-limiting one. This is why many in IT push the concept of a solution–and the analogue is this: a tool can perform a particular operation (turn a screw, hammer a nail, crimp a wire, etc.); a solution achieves a goal of the system that consists of a series of operations, which are often complex (build the wall, install the wiring, etc.). Software can be a tool or a solution. Software built as a solution contains the elements of many tools.

Given a solution that supports IPM, a pathway is put in place that facilitates breaking down the barriers that currently block effective communication between and within project teams.

The necessity of IPM

An oft-cited aphorism in business is that purpose drives profit. For those in public administration purpose drives success. What this means is that in order to become successful in any endeavor that the organization must define itself. It is the nature of the project–a planned set of interrelated tasks separately organized and financed from the larger enterprise, which is given a finite time and budget specifically to achieve a goal of research, development, production, or end state–that defines an organization’s purpose: building aircraft, dams, ships, software, roads, bridges, etc.

A small business is not so different from a project organization in a larger enterprise. Small events can have oversized effects. What this means in very real terms is that the core rules of economics will come to bear with great weight on the activities of project management. In the world in which we operate, the economics underlying both enterprises and projects punishes inefficiency. Software “tools” that support sub-optimization are inefficient and the organizations that employ them bear unnecessary risk.

The information and technology sectors have changed what is considered to be inefficient in terms of economics. At its core, information has changed the way we view and leverage information. Back in 1997 economists Brad DeLong and Michael Froomkin identified the nature of information and its impact on economics. Their concepts and observations have had incredible staying power if, for no other reason, because what they predicted has come to pass. The economic elements of excludability, rivalry, transparency have transformed how the enterprise achieves optimization.

An enterprise that is willfully ignorant of its condition is one that is at risk. Given that many projects will determine the success of the enterprise, a project that is willfully ignorant of its condition threatens the financial health and purpose of the larger organization. Businesses and public sector agencies can no longer afford not to have cohesive and actionable intelligence built on all of the elements that contribute to determining that condition. In this way IPM becomes not only essential but its deployment necessary.

In the end the reason for doing this comes down to profit on the one hand, and success on the other. Given the increasing transparency of information and the continued existence of rivalry, the trend in the economy will be to reward those that harness the potentials for information integration that have real consequences in the management of the enterprise, and to punish those who do not.

All Along the Watch Tower — Project Monitoring vs. Project Management

My two month summer blogging hiatus has come to a close. Along the way I have gathered a good bit of practical knowledge related to introducing and implementing process and technological improvements into complex project management environments. More specifically, my experience is in introducing new adaptive technologies that support the integration of essential data across the project environment–integrated project management in short–and do so by focusing on knowledge discovery in databases (KDD).

An issue that arose during these various opportunities reminded me of the commercial where a group of armed bank robbers enter a bank and have everyone lay on the floor. One of the victims whispers to a uniformed security officer, “Hey, do something!” The security officer replies, “Oh, I’m not a security guard, I’m a security monitor. I only notify people if there is a robbery.” He looks to the robbers who have a hostage and then turns back to the victim and says calmly, “There’s a robbery.”

We oftentimes face the same issues in providing project management solutions. New technologies have expanded the depth and breadth of information that is available to project management professionals. Oftentimes the implementation of these solutions get to the heart as to whether people considers themselves project managers or project monitors.

Technology, Information, and Cognitive Dissonance

This perceptual conflict oftentimes plays itself out in resistance to change in automated systems. In today’s world the question of acceptance is a bit different than when I first provided automated solutions into organizations more than 30 years ago. At that time, which represented the first modern wave of digitization, focused on simply automating previously manual functions that supported existing line-and-staff organizations. Software solutions were constructed to fit into the architecture of the social or business systems being served, regardless of whether those systems were inefficient or sub-optimal.

The challenge is a bit different today. Oftentimes new technology is paired with process changes that will transform an organization–and quite often is used as the leading edge in that initiative. The impact on work is transformative, shifting the way that the job and the system itself is perceived given the new information.

Leon Festinger in his work A Theory of Cognitive Dissonance (1957) stated that people seek psychological consistency in order to function in the real world. When faced with information or a situation that is contradictory to consistency, individuals will experience psychological discomfort. The individual can then simply adapt to the new condition by either accepting the change, adding rationalizations to connect their present perceptions to the change, or to challenge the change–either by attacking it as valid, by rejecting its conclusions, or by avoidance.

The most problematic of the reactions that can be encountered in IT project management are the last two. When I have introduced a new technology paired with process change this manifestation has usually been justified by the refrains that:

a. The new solution is too hard to understand;

b. The new solution is too detailed;

c. The new solution is too different from the incumbent technology;

d. The solution is unrelated to “my job of printing out one PowerPoint chart”;

e. “Why can’t I just continue to use my own Excel workbooks/Access database/solution”;

f. “Earned value/schedule/risk management/(add PM methodology here) doesn’t tell me what I don’t already know/looks in the rear view mirror/doesn’t add enough value/is too expensive/etc.”

For someone new to this kind of process the objections often seem daunting. But some perspective always helps. To date, I have introduced and implemented three waves of technology over the course of my career and all initially encountered resistance, only to eventually be embraced. In a paradoxical twist (some would call it divine justice, karma, or universal irony), oftentimes the previous technology I championed, which sits as the incumbent, is used as a defense against the latest innovation.

A reasonable and diligent person involved in the implementation of any technology which, after all, is also project management, must learn to monitor conditions to determine if there is good reason for resistance, or if it is a typical reaction to relatively rapid change in a traditionally static environment. The point, of course, is not only to meet organizational needs, but to achieve a high level of acceptance in software deployment–thus maximizing ROI for the organization and improving organizational effectiveness.

If process improvement is involved, an effective pairing and coordination with stakeholders is important. But such objections, while oftentimes a reaction to people receiving information they prefer not to have, are ignored at one’s own peril. This is where such change processes require both an analytical and leadership-based approach.

Technology and Cultural Change – Spock vs. Kirk

In looking at resistance one must determine whether the issue is one of technology or some reason of culture or management. Testing the intuitiveness of the UI, for example, is best accomplished by beta testing among SMEs. Clock speeds latency, reliability, accuracy, and fidelity in data, and other technological characteristics are easily measured and documented. This is the Mr. Spock side of the equation, where, in an ideal world, rationality and logic should lead one to success. Once these processes are successfully completed, however, the job is still not done.

Every successful deployment still contains within it pockets of resistance. This is the emotional part of technological innovation that oftentimes is either ignored or that managers hope to paper or plow over, usually to their sorrow. It is here that we need to focus our attention. This is the Captain Kirk part of the equation.

The most vulnerable portion of an IT project deployment happens within the initial period of inception. Rolling wave implementations that achieve quick success will often find that there is more resistance over time as each new portion of the organization is brought into the fold. There are many reasons for this.

New personnel may be going by what they observed from the initial embrace of the technology and not like the results. Perhaps buy-in was not obtained by the next group prior to their inclusion, or senior management is not fully on-board. Perhaps there is a perceived or real fear of job loss, or job transformation that was not socialized in advance. It is possible that the implementation focused too heavily on the needs of the initial group of personnel brought under the new technology, which caused the technology to lag in addressing the needs of the next wave. It could also be that the technology is sufficiently different as to represent a “culture shock”, which causes an immediate defensive reaction. If there are outsourced positions, the subcontractor may feel that its interests are threatened by the introduction of the technology. Some SMEs, having created “irreplaceable asset” barriers, may feel that their position would be eroded if they were to have to share expertise and information with other areas of the organization. Lower level employees fear that management will have unfettered access to information prior to vetting. The technology may be oversold as a panacea, rather as a means of addressing organizational or information management deficiencies. All of these reasons, and others, are motivations to explore.

There is an extensive literature on the ways to address the concerns listed above, and others. Good examples can be found here and here.

Adaptive COTS or Business Intelligence technologies, as well as rapid response teams based on Agile, go a long way in addressing and handling barriers to acceptance on the technology side. But additional efforts at socialization and senior management buy-in are essential and will be the difference maker. No amount of argumentation or will persuade people otherwise inclined to defend the status quo, even when benefits are self-evident. Leadership by information consumers–both internal and external–as well as decision-makers will win the day.

Process and Technology – Integrated Project Management and Big(ger) Data

The first wave of automation digitized simple manual efforts (word processing, charts, graphs). This resulted in an incremental increase in productivity but, more importantly, it shifted work so that administrative overhead was eliminated. There are no secretarial pools or positions as there were when I first entered the workforce.

The second and succeeding waves tackled transactional systems based on line and staff organizational structures, and work definitions. Thus, in project management, EVM systems were designed for cost analysts, scheduling apps for planners and schedulers, risk analysis software for systems engineers, and so on.

All of these waves had a focus on functionality of hard-coded software solutions. The software determined what data was important and what information could be processed from it.

The new paradigm shift is a focus on data. We see this through the buzz phrase “Big Data”.  But what does that mean? It means that all of the data that the organization or enterprise collects has information value. Deriving that information value, and then determining its relevance and whether it provides actionable intelligence, is of importance to the organization.

Thus, implementations of data-focused solutions represent not only a shift in the way that work is performed, but also how information is used, and how the health and performance of the organization is assessed. Horizontal information integration across domains provides insights that were not apparent in the past when data was served to satisfy the needs of specialized domains and SMEs. New vulnerabilities and risks are uncovered through integration. This is particularly clear when implementing integrated project management (IPM) solutions.

A pause in providing a definition is in order, especially since IPM is gaining traction, and so large lazy and entrenched incumbents adjust their marketing in the hope of muddying the waters to fit their square peg focused and hard-coded solutions into the round hole of flexible IPM solutions.

Integrated Project Management are the processes and integration of information necessary to derive actionable intelligence from all of the relevant cross-domain information involved in the project organization. This includes cost performance, schedule performance, financial performance and execution, contract implementation, milestone achievement, resource management, and technical performance. Actionable intelligence is that information that is relevant to the project decision-making authority which effectively identifies specific probable qualitative and quantitative risks, risk impact, and risk handling necessary to make project trade-offs, project re-baselining or re-scope, cost-as-an-independent variable (CAIV), or project cancellation decisions. Underlying all of this are feedback loop systems assessments to ensure that there is integrity and fidelity in our business systems–both human and digital.

No doubt, we have a ways to go to get to this condition, but organizations are getting there. What it will take is a change the way leadership views its role, in rewriting traditional project management job descriptions, cross-domain training and mentoring, and in enforcing both for ourselves and in others the dedication to the ethics that are necessary to do the job.

Practice and Ethics in Project Management within Public Administration

The final aspect of implementations of project management systems that is often overlooked, and which oftentimes frames the environment that we are attempting to transform, concerns ethical behavior in project management. It is an aspect of project success as necessary as any performance metric, and it is one for which leadership within an organization sets the tone.

My own expertise in project management has concerned itself in most cases with project management in the field of public administration, though as a businessman I also have experience in the commercial world. Let’s take public administration first since, I think, it is the most straightforward.

When I wore a uniform as a commissioned Naval officer I realized that in my position and duties that I was merely an instrument of the U.S. Navy, and its constitutional and legal underpinnings. My own interests were separate from, and needed to be firewalled from, the execution of my official duties. When I have observed deficiencies in the behavior of others in similar positions, this is the dichotomy that often fails to be inculcated in the individual.

When enlisted personnel salute a commissioned officer they are not saluting the person, they are saluting and showing respect to the rank and position. The officer must earn respect as an individual. Having risen from the enlisted ranks, these were the aspects of leadership that were driven home to me in observing this dynamic: in order to become a good leader, one must first have been a good follower; you must demonstrate trust and respect to earn trust and respect. One must act ethically.

Oftentimes officials in other governmental entities–elected officials (especially), judges, and law enforcement–often fail to understand this point and hence fail this very basic rule of public behavior. The law and their position deserves respect. The behavior and actions of the individuals in their office will determine whether they personally should be shown respect. If an individual abuses their position or the exercise of discretion, they are not worthy of respect, with the danger that they will delegitimize and bring discredit to the office or position.

But earning respect is only one aspect of this understanding in ethical behavior in public administration. It also means that one will make decisions based on the law, ethical principles, and public policy regardless of whether one personally agrees or disagrees with the resulting conclusion of those criteria. That an individual will also apply a similar criteria whether or not the decision will adversely impact their own personal interests or those of associates, friends, or family is also part of weight of ethical behavior.

Finally, in applying the ethical test rule, one must also accept responsibility and accountability in executing one’s duties. This means being diligent, constantly striving for excellence and improvement, leading by example, and to always represent the public interest. Note that ego, personal preference, opinion, or bias, self-interest, or other such concerns have no place in the ethical exercise of public administration.

So what does that mean for project management? The answer goes to the heart of whether one views himself or herself as a project manager or project monitor. In public administration the program manager has a unique set of responsibilities tied to the acquisition of technologies that is rarely replicated in private industry. Oftentimes this involves shepherding a complex effort via contractual agreements that involve large specialized businesses–and often a number of subcontractors–across several years of research and development before a final product is ready for production and deployment.

The primary role in this case is to ensure that the effort is making progress and executing the program toward the goal, ensuring accountability of the funds being expended, which were appropriated for the specific effort by Congress, to ensure that the effort intended by those expenditures through the contractual agreements are in compliance, to identify and handle risks that may manifest to bring the effort into line with the cost, schedule, and technical baselines, all the while staying within the program’s framing assumptions. In addition, the program manager must coordinate with operational managers who are anticipating the deployment of the end item being developed, manage expectations, and determine how best to plan for sustainability once the effort goes to production and deployment. This is, of course, a brief summary of the extensive duties involved.

Meeting these responsibilities requires diligence, information that provides actionable intelligence, and a great deal of subject matter expertise. Finding and handling risks, determining if the baseline is executable, maintaining the integrity of the effort–all require leadership and skill. This is known as project management.

Project monitoring, by contrast, is acceptance of information provided by self-interested parties without verification, of limiting the consumption and processing of essential project performance information, of demurring to any information of a negative nature regarding project performance or risk, of settling for less than an optimal management environment, and using these tactics to, euphemistically, kick the ball down the court to the next project manager in the hope that the impact of negligence falls on someone else’s watch. Project monitoring is unethical behavior in public administration.

Practice and Ethics in Project Management within Private Industry

The focus in private industry is a bit different since self-interest abounds and is rewarded. But there are ethical rules that apply, and which a business person in project management would be well-served to apply.

The responsibility of the executive or officers in a business is to the uphold the interests of the enterprise’s customers, its employees, and its shareholders. Oftentimes business owners will place unequal weighting to these interests, but the best businesses view these responsibilities as being in fine balance.

For example, aside from the legal issues, ethics demands that in making a commitment in providing supplies and services there are a host of obligations that go along with that transaction–honest representation, warranty, and a commitment to provide what was promised. For employees, the commitments made regarding the conditions of employment and to reward employees appropriately for their contribution to the enterprise. For stockholders it is to conduct the business in such as way as to avoid placing its fiduciary position and its ability to act as a going concern in avoidable danger.

For project managers the responsibility within these ethical constraints is to honestly assess and communicate to the enterprise’s officers project performance, whether the effort will achieve the desired qualitative results within budgetary and time constraints, and, from a private industry perspective, handle most of the issues articulated for the project manager in the section on public administration above. The customer is different in this scenario, oftentimes internal, especially when eliminating companies that serve the project management verticals in public administration. Oftentimes the issues and supporting systems are less complex because the scale is, on the whole, smaller.

There are exceptions, of course, to the issue of scaling. Some construction, shipbuilding, and energy projects approach the complexity of some public sector programs. Space X and other efforts are other examples. But the focus there is financial from the perspective of the profit motive–not from the perspective of meeting the goals of some public interest involving health, safety, or welfare, and so the measures of measurement will be different, though the need for accountability and diligence is no less urgent. In may ways such behavior is more urgent given that failure may result in the failure of the entire enterprise.

Yet, the basic issue is the same: are you a project manager or a project monitor? Diligence, leadership, and ethical behavior (which is essential to leadership) are the keys. Project monitoring most often results in failure, and with good reason. It is a failure of both practice and ethics.