Back to School Daze Blogging–DCMA Investigation on POGO, DDSTOP, $600 Ashtrays,and Epistemic Sunk Costs

Family summer visits and trips are in the rear view–as well as the simultaneous demands of balancing the responsibilities of a, you know, day job–and so it is time to take up blogging once again.

I will return to my running topic of Integrated Program and Project Management in short order, but a topic of more immediate interest concerns the article that appeared on the website for pogo.org last week entitled “Pentagon’s Contracting Gurus Mismanaged Their Own Contracts.” Such provocative headlines are part and parcel of organizations like POGO, which have an agenda that seems to cross the line between reasonable concern and unhinged outrage with a tinge conspiracy mongering. But the content of the article itself is accurate and well written, if also somewhat ripe with overstatement, so I think it useful to unpack what it says and what it means.

(more…)

Post-Workshop Talking Blues — No Bucks, No Buck Rogers: Cashflow Analysis in Projects (Somewhat Wonkish)

When I used this analogy the week before last during the last Integrated Project Management Workshop in the D.C. area I was accused of dating myself–and perhaps it is true. For those wondering the quote was popularized by the 1983 movie The Right Stuff, which was based on the 1979 book written by Tom Wolfe of the same title. The book and movie was about the beginnings of the U.S. space program culminating in the creation of NASA and the Project Mercury program.

(more…)

Money for Nothing — Project Performance Data and Efficiencies in Timeliness

I operate in a well regulated industry focused on project management. What this means practically is that there are data streams that flow from the R&D activities, recording planning and progress, via control and analytical systems to both management and customer. The contract type in most cases is Cost Plus, with cost and schedule risk often flowing to the customer in the form of cost overruns and schedule slippages.

(more…)

Synergy — The Economics of Integrated Project Management

The hot topic lately in meetings and the odd conference on Integrated Project Management (IPM) often focuses on the mechanics of achieving that state, bound by the implied definition of current regulation, which has also become–not surprisingly–practice. I think this is a laudable goal, particularly given both the casual resistance to change (which always there by definition to some extent) and in the most extreme cases a kind of apathy.

(more…)

All Along the Watch Tower — Project Monitoring vs. Project Management

My two month summer blogging hiatus has come to a close. Along the way I have gathered a good bit of practical knowledge related to introducing and implementing process and technological improvements into complex project management environments. More specifically, my experience is in introducing new adaptive technologies that support the integration of essential data across the project environment–integrated project management in short–and do so by focusing on knowledge discovery in databases (KDD).

(more…)

Rear View Mirror — Correcting a Project Management Fallacy

“The past is never dead. It’s not even past.” —  William Faulkner, Requiem for a Nun

Over the years I and others have briefed project managers on project performance using KPPs, earned value management, schedule analysis, business analytics, and what we now call predictive analytics. Oftentimes, some set of figures will be critiqued as being ineffective or unhelpful; that the analytics “only look in the rear view mirror” and that they “tell me what I already know.”

(more…)

Takin’ Care of Business — Information Economics in Project Management

Neoclassical economics abhors inefficiency, and yet inefficiencies exist.  Among the core issues that create inefficiencies is the asymmetrical nature of information.  Asymmetry is an accepted cornerstone of economics that leads to inefficiency.  We can see in our daily lives and employment the effects of one party in a transaction having more information than the other:  knowing whether the used car you are buying is a lemon, measuring risk in the purchase of an investment and, apropos to this post, identifying how our information systems allow us to manage complex projects.

(more…)

Technical Foul — It’s Time for TPI in EVM

For more than 40 years the discipline of earned value management (EVM) has gone through a number of changes in its descriptions, governance, and procedures.  During that same time its community has been resistant to improvements in its methodology or to changes that extend its value when taking into account other methods that either augment its usefulness, or that potentially provide more utility in the area of performance management.  This has been especially the case where it is suggested that EVM is just one of many methodologies that contribute to this assessment under a more holistic approach.

(more…)

New York Times Says Research and Development Is Hard…but maybe not

At least that is what a reader is led to believe by reading this article that appeared over the weekend.  For those of you who didn’t catch it, Alphabet, which formerly had an R&D shop under the old Google moniker known as Google X, does pure R&D.  According to the reporter, one Conor Doughtery, the problem, you see, is that R&D doesn’t always translate into a direct short-term profit.  He then makes this absurd statement:  “Building a research division is an old and often unsuccessful concept.”  He knows this because some professor at Arizona State University–that world-leading hotbed of innovation and high tech–told him so.  (Yes, there is sarcasm in that sentence).

(more…)

Technical Ecstacy — Technical Performance and Earned Value

As many of my colleagues in project management know, I wrote a series of articles on the application of technical performance risk in project management back in 1997, one of which made me an award recipient from the institution now known as Defense Acquisition University.  Over the years various researchers and project organizations have asked me if I have any additional thoughts on the subject and the response up until now has been: no.  From a practical standpoint, other responsibilities took me away from the domain of determining the best way of recording technical achievement in complex projects.  Furthermore, I felt that the field was not ripe for further development until there were mathematics and statistical methods that could better approach the behavior of complex adaptive systems.

(more…)